| Assessment Year | 1998 |
|---|---|
| Principal Product | Wrappers |
| NAICS |
n/a
|
| SIC | 2653: Corrugated and Solid Fiber Boxes |
| Sales Range | $10 M to 50M |
| # of Employees | 103 |
| Plant Area |
105,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $121,382 | 2,422,333 |
kWh
|
$0.050 |
| Electricity Demand | $80,478 | 6,588 |
kW-mo/yr
|
$12.22 |
| Electricity Fees | $33,785 | - |
|
- |
| Natural Gas | $77,969 | 17,951 |
MMBtu
|
$4.34 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $28,803 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7111: Reduce illumination to minimum necessary levels | $5,378 | $2,188 |
$5,184
94,959
kWh
|
$194
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,806 | $500 |
$1,551
37,222
kWh
|
$1,255
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7243: Improve air circulation with destratification fans / other methods | $6,709 | $6,300 | - | - |
$6,709
-
MMBtu
|
- | - | |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $3,138 | $4,120 | - | - |
$3,138
-
MMBtu
|
- | - | |
| 05 | 3.3122: Use filtration, centrifuging to remove contaminants | $812 | $800 | - | - | - | - |
$812
-
Tgal
|
|
| 06 | 3.4155: Meter waste water | $599 | $900 | - | - | - | - |
$599
-
Tgal
|
|
| 07 | 4.431: Train operators for maximum operating efficiency | $5,200 | $100 | - | - | - | $5,200 | - | |
| 08 | 4.431: Train operators for maximum operating efficiency | $4,161 | $200 | - | - | - | $4,161 | - | |
| TOTAL RECOMMENDED | $28,803 | $15,108 |
$6,735
132,181
kWh
|
$1,449
-
kW-mo/yr
|
$9,847
-
MMBtu
|
$9,361 |
$1,411
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs