Assessment Year | 2018 |
---|---|
Principal Product | Waste Water Treatment |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $10 M to 50M |
# of Employees | 9 |
Plant Area |
90,000
ft2
|
Annual Production | 1,095,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $196,244 | 2,141,360 |
kWh
|
$0.092 | |
Electricity Demand | $29,300 | 4,475 |
kW-mo/yr
|
$6.55 | |
Natural Gas | $24,688 | 4,785 |
MMBtu
|
$5.16 | |
Waste Disposal Costs | |||||
Solid Waste (non-haz) | $90,000 | 6,000,000 |
lb
|
$0.015 | |
TOTAL YEARLY COSTS | $340,232 | ||||
RECOMMENDED SAVINGS* | $152,776 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $103,786 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $84,000 | $3,000 | - | - | - |
$90,000
-
lb
|
$(-6,000.0) | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $45,746 | $111,500 |
$41,665
454,856
kWh
|
$4,081
-
kW-mo/yr
|
- | - | - | |
03 | 2.7135: Install occupancy sensors | $6,517 | $3,640 |
$5,620
61,353
kWh
|
$897
-
kW-mo/yr
|
- | - | - | |
04 | 2.4313: Provide proper maintenance of motor driven equipment | $4,668 | $19,300 |
$4,249
46,390
kWh
|
$419
-
kW-mo/yr
|
- | - | - | |
05 | 2.4157: Establish a predictive maintenance program | $4,560 | $1,000 |
$4,154
45,348
kWh
|
$406
-
kW-mo/yr
|
- | - | - | |
06 | 2.7264: Interlock heating and air conditioning systems to prevent simultaneous operation | $2,563 | $11,400 |
$1,348
14,717
kWh
|
$131
-
kW-mo/yr
|
$1,084
-
MMBtu
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,998 | $7,133 |
$1,670
18,228
kWh
|
$328
-
kW-mo/yr
|
- | - | - | |
08 | 2.4151: Develop a repair/replace policy | $2,043 | $721 |
$1,860
20,305
kWh
|
$183
-
kW-mo/yr
|
- | - | - | |
09 | 2.1233: Analyze flue gas for proper air/fuel ratio | $681 | $3,000 | - | - |
$681
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $152,776 | $160,694 |
$60,566
661,197
kWh
|
$6,445
-
kW-mo/yr
|
$1,765
-
MMBtu
|
$90,000
-
lb
|
$(-6,000.0) | ||
TOTAL IMPLEMENTED | $103,786 | $34,794 |
$17,553
191,624
kWh
|
$2,233
-
kW-mo/yr
|
- |
$90,000
-
lb
|
$(-6,000.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs