ITAC Assessment: WV0558
ITAC logo
ITAC Assessment: WV0558
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product water
NAICS 221320: Sewage Treatment Facilities
SIC 4941: Water Supply
Sales Range $1
M
to 5
M
# of Employees 6
Plant Area 21,442
ft2
Annual Production 730,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $126,122 1,395,154
kWh
Natural Gas $3,676 796
MMBtu
Waste Disposal Costs
Solid Waste (non-haz) $17,760 1,611,475
lb
TOTAL YEARLY COSTS $147,558
RECOMMENDED SAVINGS* $36,414 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,855

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 3.6193: Install equipment (eg compactor) to reduce disposal costs $17,760 $81,750 - - $17,760
-
lb
-
02 2.4313: Provide proper maintenance of motor driven equipment $10,332 $20,570 $10,332
114,296
kWh
- - -
03 2.4157: Establish a predictive maintenance program $3,223 $1,000 $4,038
44,672
kWh
- - $(-815.0)
04 2.7135: Install occupancy sensors $2,061 $1,265 $2,061
22,801
kWh
- - -
05 2.7264: Interlock heating and air conditioning systems to prevent simultaneous operation $1,726 $7,488 $1,407
15,565
kWh
$319
-
MMBtu
- -
06 2.4151: Develop a repair/replace policy $629 $579 $909
10,051
kWh
- - $(-280.0)
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $406 $2,005 $406
4,496
kWh
- - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $277 $522 $277
3,061
kWh
- - -
TOTAL RECOMMENDED $36,414 $115,179 $19,430
214,942
kWh
$319
-
MMBtu
$17,760
-
lb
$(-1,095.0)
TOTAL IMPLEMENTED $5,855 $9,589 $6,631
73,349
kWh
$319
-
MMBtu
- $(-1,095.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs