| Assessment Year | 2017 |
|---|---|
| Principal Product | Hand Tools |
| NAICS | 332216: Saw Blade and Handtool Manufacturing |
| SIC | 3423: Hand and Edge Tools, Except Machine Tools and Handsaws |
| Sales Range | $10 M to 50M |
| # of Employees | 14 |
| Plant Area |
900,000
ft2
|
| Annual Production | 25,550
units
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | West Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $25,184 | 336,487 |
kWh
|
$0.075 | |
| Electricity Demand | $19,153 | 2,105 |
kW-mo/yr
|
$9.10 | |
| Electricity Fees | $252 | - |
|
- | |
| Natural Gas | $50,170 | 8,837 |
MMBtu
|
$5.68 | |
| Other Gas | $8,952 | 414 |
MMBtu
|
$21.62 | |
| Waste Disposal Costs | |||||
| Water Usage | $96 | 18 |
Tgal
|
$5.33 | |
| Water Disposal | $162 | 18 |
Tgal
|
$9.00 | |
| TOTAL YEARLY COSTS | $103,969 | ||||
| RECOMMENDED SAVINGS* | $35,797 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $11,408 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $23,992 | $112,000 | - | - |
$23,992
-
MMBtu
|
- | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,431 | $10,658 |
$3,138
41,953
kWh
|
$2,293
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,017 | $210 |
$2,324
31,063
kWh
|
$1,693
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,097 | - |
$624
8,344
kWh
|
$473
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $496 | $50 |
$287
3,843
kWh
|
$209
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.4224: Upgrade controls on compressors | $397 | $1,500 |
$397
5,302
kWh
|
- | - | - | - | - | |
| 07 | 3.4151: Minimize water usage | $239 | $1,050 | - | - | - |
$96
-
Tgal
|
$162
-
Tgal
|
$(-19.0) | |
| 08 | 2.4151: Develop a repair/replace policy | $128 | $594 |
$160
2,134
kWh
|
$118
-
kW-mo/yr
|
- | - | - | $(-150.0) | |
| TOTAL RECOMMENDED | $35,797 | $126,062 |
$6,930
92,639
kWh
|
$4,786
-
kW-mo/yr
|
$23,992
-
MMBtu
|
$96
-
Tgal
|
$162
-
Tgal
|
$(-169.0) | ||
| TOTAL IMPLEMENTED | $11,408 | $12,562 |
$6,533
87,337
kWh
|
$4,786
-
kW-mo/yr
|
- |
$96
-
Tgal
|
$162
-
Tgal
|
$(-169.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs