Assessment Year | 2017 |
---|---|
Principal Product | Metal Wire |
NAICS | 332618: Other Fabricated Wire Product Manufacturing |
SIC | 3496: Miscellaneous Fabricated Wire Products |
Sales Range | $50 M to 100M |
# of Employees | 140 |
Plant Area |
300,000
ft2
|
Annual Production | 4,800,000
units
|
Production Hrs. Annual | 4,500
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $306,805 | 4,474,218 |
kWh
|
$0.069 | |
Fuel Oil #1 | $247,045 | 8,647 |
MMBtu
|
$28.57 | |
Waste Disposal Costs | |||||
Water Usage | $205 | 75,000 |
Tgal
|
$0.003 | |
Water Disposal | $813 | 75 |
Tgal
|
$10.84 | |
Other Liquid (non-haz) | $15,038 | 15,038 |
gal
|
$1.00 | |
Solid Waste (non-haz) | $1,800 | 12,000 |
lb
|
$0.15 | |
TOTAL YEARLY COSTS | $571,706 | ||||
RECOMMENDED SAVINGS* | $44,916 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $4,283 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #1 Savings | Water Usage Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7313: Recycle air for heating, ventilation and air conditioning | $14,599 | $10,000 | - |
$14,599
-
MMBtu
|
- | - | - | - | - | - | |
02 | 3.3131: Use evaporation to concentrate material | $11,734 | $40,000 | - | - | - | - |
$15,038
-
gal
|
$(-1,800.0)
-
lb
|
$(-1,504.0) | - | |
03 | 2.2123: Insulate feedwater tank | $7,035 | $3,286 |
$7,035
102,550
kWh
|
- | - | - | - | - | - | - | |
04 | 2.4224: Upgrade controls on compressors | $3,005 | $3,800 |
$3,005
43,800
kWh
|
- | - | - | - | - | - | - | |
05 | 2.4224: Upgrade controls on compressors | $2,223 | $6,400 |
$2,223
32,400
kWh
|
- | - | - | - | - | - | - | |
06 | 2.4151: Develop a repair/replace policy | $1,394 | $635 |
$1,574
22,950
kWh
|
- | - | - | - | - | $(-180.0) | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,287 | $713 |
$1,287
18,766
kWh
|
- | - | - | - | - | - | - | |
08 | 2.4322: Use or replace with energy efficient substitutes | $1,154 | $5,500 |
$1,154
16,825
kWh
|
- | - | - | - | - | - | - | |
09 | 3.3131: Use evaporation to concentrate material | $883 | $3,150 | - | - |
$205
-
Tgal
|
$813
-
Tgal
|
- | - | - | $(-135.0) | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $846 | $2,370 |
$846
12,334
kWh
|
- | - | - | - | - | - | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $324 | $1,001 |
$324
4,721
kWh
|
- | - | - | - | - | - | - | |
12 | 2.4231: Reduce the pressure of compressed air to the minimum required | $303 | $60 |
$303
4,415
kWh
|
- | - | - | - | - | - | - | |
13 | 2.7135: Install occupancy sensors | $129 | $135 |
$129
1,887
kWh
|
- | - | - | - | - | - | - | |
TOTAL RECOMMENDED | $44,916 | $77,050 |
$17,880
260,648
kWh
|
$14,599
-
MMBtu
|
$205
-
Tgal
|
$813
-
Tgal
|
$15,038
-
gal
|
$(-1,800.0)
-
lb
|
$(-1,684.0) | $(-135.0) | ||
TOTAL IMPLEMENTED | $4,283 | $4,914 |
$4,463
65,073
kWh
|
- | - | - | - | - | $(-180.0) | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #1 Savings | Water Usage Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs