ITAC Assessment: WV0517
ITAC logo
ITAC Assessment: WV0517
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Lumber
NAICS 321113: Sawmills
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 126
Plant Area 40,000
ft2
Annual Production 18,000
thousand feet
Production Hrs. Annual 2,678
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $314,377 9,466,174
kWh
Electricity Demand $432,504 28,229
kW-mo/yr
Wood $91,250 58,400
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $57,510 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $31,142

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Wood Savings Personnel Changes Savings
01 2.1116: Improve combustion control capability $22,825 $54,000 - - $22,825
-
MMBtu
-
02 2.4157: Establish a predictive maintenance program $7,474 $1,000 $6,716
202,293
kWh
$4,351
-
kW-mo/yr
- $(-3,593.0)
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $14,320 - $4,668
140,589
kWh
$9,652
-
kW-mo/yr
- -
04 2.4151: Develop a repair/replace policy $5,859 $1,478 $1,988
59,890
kWh
$4,351
-
kW-mo/yr
- $(-480.0)
05 2.4224: Upgrade controls on compressors $2,584 $5,000 $2,584
77,845
kWh
- - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,573 $450 $439
13,231
kWh
$1,134
-
kW-mo/yr
- -
07 2.7135: Install occupancy sensors $1,069 $260 $1,069
33,207
kWh
- - -
08 2.2511: Insulate bare equipment $959 $1,940 - - $959
-
MMBtu
-
09 2.4231: Reduce the pressure of compressed air to the minimum required $847 $60 $265
7,984
kWh
$582
-
kW-mo/yr
- -
TOTAL RECOMMENDED $57,510 $64,188 $17,729
535,039
kWh
$20,070
-
kW-mo/yr
$23,784
-
MMBtu
$(-4,073.0)
TOTAL IMPLEMENTED $31,142 $3,248 $15,145
457,194
kWh
$20,070
-
kW-mo/yr
- $(-4,073.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Wood Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs