Assessment Year | 2015 |
---|---|
Principal Product | Motors and Plastics |
NAICS | 335312: Motor and Generator Manufacturing |
SIC | 3621: Motors and Generators |
Sales Range | $10 M to 50M |
# of Employees | 105 |
Plant Area |
46,500
ft2
|
Annual Production | 440,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $146,910 | 2,008,800 |
kWh
|
$0.073 |
Electricity Demand | $53,154 | 4,998 |
kW-mo/yr
|
$10.64 |
Natural Gas | $52,832 | 7,478 |
MMBtu
|
$7.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,890 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,627 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,361 | $688 |
$3,403
46,550
kWh
|
$958
-
kW-mo/yr
|
- | |
02 | 2.4322: Use or replace with energy efficient substitutes | $4,286 | $11,500 |
$3,350
45,822
kWh
|
$936
-
kW-mo/yr
|
- | |
03 | 2.4224: Upgrade controls on compressors | $3,646 | $5,000 |
$2,848
38,962
kWh
|
$798
-
kW-mo/yr
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,801 | $15,300 |
$2,482
33,954
kWh
|
$1,319
-
kW-mo/yr
|
- | |
05 | 2.7135: Install occupancy sensors | $1,756 | $420 |
$1,373
18,786
kWh
|
$383
-
kW-mo/yr
|
- | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,663 | - |
$1,301
17,798
kWh
|
$362
-
kW-mo/yr
|
- | |
07 | 2.4151: Develop a repair/replace policy | $1,005 | $256 |
$900
12,314
kWh
|
$255
-
kW-mo/yr
|
$(-150.0) | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $842 | $50 |
$661
9,037
kWh
|
$181
-
kW-mo/yr
|
- | |
09 | 2.4239: Eliminate or reduce compressed air usage | $530 | $2,104 |
$413
5,655
kWh
|
$117
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $21,890 | $35,318 |
$16,731
228,878
kWh
|
$5,309
-
kW-mo/yr
|
$(-150.0) | ||
TOTAL IMPLEMENTED | $9,627 | $1,414 |
$7,638
104,485
kWh
|
$2,139
-
kW-mo/yr
|
$(-150.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs