| Assessment Year | 1994 |
|---|---|
| Principal Product | Automotive and industrial acoustic insulation rolls, formed |
| NAICS |
n/a
|
| SIC | 3229: Pressed and Blown Glass and Glassware, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 480 |
| Plant Area |
300,000
ft2
|
| Annual Production | 12,000,000
lb
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $517,488 | 17,114,303 |
kWh
|
$0.030 |
| Natural Gas | $739,668 | 205,349 |
MMBtu
|
$3.60 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $141,113 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $102,289 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $7,262 | $4,455 |
$7,262
242,087
kWh
|
- | - | - | - | - | - | |
| 02 | 2.2511: Insulate bare equipment | $4,449 | $200 |
$4,449
148,300
kWh
|
- | - | - | - | - | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,344 | $1,680 |
$4,344
144,783
kWh
|
- | - | - | - | - | - | |
| 04 | 2.7261: Install timers and/or thermostats | $1,318 | $700 | - |
$1,318
-
MMBtu
|
- | - | - | - | - | |
| 05 | 2.6218: Turn off equipment when not in use | $1,300 | - | - |
$1,300
-
MMBtu
|
- | - | - | - | - | |
| 06 | 2.7124: Make a practice of turning off lights when not needed | $2,523 | $3,350 |
$2,523
84,115
kWh
|
- | - | - | - | - | - | |
| 07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $56,576 | $32,240 | - | - | - | - | - |
$56,576
-
lb
|
- | |
| 08 | 3.4131: Minimize contamination of water before treatment | $34,098 | $45,100 | - | - | - |
$34,098
-
gal
|
- | - | - | |
| 09 | 3.7212: Improved material handling (mixing and transfer) | $18,473 | $5,000 | - | - | - | - | - | - | $18,473 | |
| 10 | 3.4113: Treat and reuse rinse waters | $7,445 | $12,650 | - | - |
$7,445
-
Tgal
|
- | - | - | - | |
| 11 | 3.8211: Convert to aqueous cleaning system | $3,325 | $3,000 | - | - | - | - |
$3,325
-
gal
|
- | - | |
| TOTAL RECOMMENDED | $141,113 | $108,375 |
$18,578
619,285
kWh
|
$2,618
-
MMBtu
|
$7,445
-
Tgal
|
$34,098
-
gal
|
$3,325
-
gal
|
$56,576
-
lb
|
$18,473 | ||
| TOTAL IMPLEMENTED | $102,289 | $84,590 |
$6,972
232,415
kWh
|
$1,318
-
MMBtu
|
- |
$34,098
-
gal
|
$3,325
-
gal
|
$56,576
-
lb
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs