ITAC Assessment: WV0507
ITAC logo
ITAC Assessment: WV0507
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Polypropylene
NAICS 325211: Plastics Material and Resin Manufacturing
SIC 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers
Sales Range $100
M
to 500
M
# of Employees 120
Plant Area 4,617,000
ft2
Annual Production 569,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $3,344,327 82,396,800
kWh
Electricity Demand $1,522,858 137,062
kW-mo/yr
Natural Gas $2,285,540 495,713
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $907,840 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $181,157

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings
01 2.2414: Use waste heat from hot flue gases to preheat $352,153 $1,664,938 - - $352,153
-
MMBtu
- -
02 2.2121: Increase amount of condensate returned $161,509 $150,000 - - $155,509
-
MMBtu
$6,000
-
gal
-
03 2.2414: Use waste heat from hot flue gases to preheat $71,462 $301,590 $(-439.0)
(-10,825)
kWh
$(-167.0)
-
kW-mo/yr
$72,068
-
MMBtu
- -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $90,956 $60,015 $66,158
1,629,517
kWh
$24,798
-
kW-mo/yr
- - -
05 2.1233: Analyze flue gas for proper air/fuel ratio $53,644 $4,100 - - $53,748
-
MMBtu
- $(-104.0)
06 2.7142: Utilize higher efficiency lamps and/or ballasts $49,825 $65,562 $36,237
892,527
kWh
$13,588
-
kW-mo/yr
- - -
07 2.4157: Establish a predictive maintenance program $32,498 $1,000 $25,970
639,651
kWh
$9,732
-
kW-mo/yr
- - $(-3,204.0)
08 2.2113: Repair or replace steam traps $26,405 $14,973 - - $28,720
-
MMBtu
- $(-2,315.0)
09 2.4151: Develop a repair/replace policy $25,719 $861 $19,920
490,641
kWh
$7,466
-
kW-mo/yr
- - $(-1,667.0)
10 2.4111: Utilize energy-efficient belts and other improved mechanisms $18,016 - $13,105
322,780
kWh
$4,911
-
kW-mo/yr
- - -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $15,713 $6,794 $11,425
281,398
kWh
$4,288
-
kW-mo/yr
- - -
12 2.4231: Reduce the pressure of compressed air to the minimum required $3,922 $278 $2,855
70,319
kWh
$1,067
-
kW-mo/yr
- - -
13 2.2511: Insulate bare equipment $3,273 $6,566 - - $3,273
-
MMBtu
- -
14 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,967 $252 $1,430
35,223
kWh
$537
-
kW-mo/yr
- - -
15 2.4221: Install compressor air intakes in coolest locations $778 $597 $567
13,976
kWh
$211
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $907,840 $2,277,526 $177,228
4,365,207
kWh
$66,431
-
kW-mo/yr
$665,471
-
MMBtu
$6,000
-
gal
$(-7,290.0)
TOTAL IMPLEMENTED $181,157 $34,824 $74,705
1,840,012
kWh
$28,001
-
kW-mo/yr
$85,741
-
MMBtu
- $(-7,290.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs