Assessment Year | 2013 |
---|---|
Principal Product | Refined Cane Sugar |
NAICS | 311314: Cane Sugar Manufacturing |
SIC | 2062: Cane Sugar Refining |
Sales Range | greater than $500 M |
# of Employees | 442 |
Plant Area |
1,000,000
ft2
|
Annual Production | 2,375,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $422,742 | 7,713,100 |
kWh
|
$0.055 |
Electricity Demand | $72,098 | 29,916 |
kW-mo/yr
|
$2.41 |
Natural Gas | $11,586,203 | 2,037,824 |
MMBtu
|
$5.69 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $777,140 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $169,250 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $298,848 | $180,000 |
$(-41,493.0)
(-757,035)
kWh
|
$(-2,499.0)
-
kW-mo/yr
|
$342,840
-
MMBtu
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $167,190 | $95,000 |
$167,190
3,050,363
kWh
|
- | - | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $75,533 | $77,000 |
$75,533
1,378,094
kWh
|
- | - | - | |
04 | 2.4224: Upgrade controls on compressors | $65,843 | $50,000 |
$61,920
1,129,721
kWh
|
$3,923
-
kW-mo/yr
|
- | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $57,184 | - |
$53,935
984,041
kWh
|
$3,249
-
kW-mo/yr
|
- | - | |
06 | 2.2113: Repair or replace steam traps | $42,971 | $6,850 | - | - |
$43,346
-
MMBtu
|
$(-375.0) | |
07 | 2.2136: Install / repair insulation on steam lines | $25,992 | $29,385 | - | - |
$25,992
-
MMBtu
|
- | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,934 | $15,779 |
$14,086
256,998
kWh
|
$848
-
kW-mo/yr
|
- | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $13,970 | $1,530 |
$13,177
240,421
kWh
|
$793
-
kW-mo/yr
|
- | - | |
10 | 2.4151: Develop a repair/replace policy | $7,809 | $8,200 |
$7,932
144,725
kWh
|
$477
-
kW-mo/yr
|
- | $(-600.0) | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,390 | $7,119 |
$6,026
109,937
kWh
|
$364
-
kW-mo/yr
|
- | - | |
12 | 2.4239: Eliminate or reduce compressed air usage | $476 | $604 |
$476
8,685
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $777,140 | $471,467 |
$358,782
6,545,950
kWh
|
$7,155
-
kW-mo/yr
|
$412,178
-
MMBtu
|
$(-975.0) | ||
TOTAL IMPLEMENTED | $169,250 | $68,863 |
$95,156
1,736,122
kWh
|
$5,731
-
kW-mo/yr
|
$69,338
-
MMBtu
|
$(-975.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs