ITAC Assessment: WV0450
ITAC logo
ITAC Assessment: WV0450
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product coal tar pitch and creosote solutions
NAICS 325194: Cyclic Crude, Intermediate, and Gum and Wood Chemical Manufacturing
SIC 2865: Cyclic Organic Crudes and Intermediates, and Organic Dyes and Pigments
Sales Range $50
M
to 100
M
# of Employees 55
Plant Area 696,960
ft2
Annual Production 187,393
ton
Production Hrs. Annual 8,760
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $731,248 11,541,000
kWh
Natural Gas $1,287,994 200,931
MMBtu
Other Energy $2,233,606 300,388
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $740,671 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $333,287

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Energy Savings Personnel Changes Savings Administrative Changes Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $173,557 $1,000 - $173,737
-
MMBtu
- $(-180.0) -
02 2.2422: Use waste heat from hot flue gases to generate steam $141,590 $210,000 - - $146,590
-
MMBtu
$(-5,000.0) -
03 2.2414: Use waste heat from hot flue gases to preheat $130,899 $157,320 - $130,899
-
MMBtu
- - -
04 2.5194: Redesign process $102,043 $230,000 $(-7,584.0)
(-119,701)
kWh
$32,198
-
MMBtu
$89,399
-
MMBtu
- $(-11,970.0)
05 2.3412: Use waste heat to produce steam to drive a steam turbine-generator $97,121 $400,000 $107,121
1,690,680
kWh
- - $(-10,000.0) -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $36,667 $21,800 $36,667
578,708
kWh
- - - -
07 2.7132: Install timers on light switches in little used areas $11,389 $6,500 $11,389
179,755
kWh
- - - -
08 2.4157: Establish a predictive maintenance program $10,199 $1,000 $11,812
186,420
kWh
- - $(-1,613.0) -
09 2.2414: Use waste heat from hot flue gases to preheat $9,686 $21,120 - $9,686
-
MMBtu
- - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $8,953 $18,267 $8,953
141,305
kWh
- - - -
11 2.4151: Develop a repair/replace policy $8,489 $1,210 $9,449
149,140
kWh
- - $(-960.0) -
12 2.7241: Install outside air damper / economizer on hvac unit $7,314 $3,360 $7,314
115,442
kWh
- - - -
13 2.4221: Install compressor air intakes in coolest locations $2,764 $1,800 $2,764
43,627
kWh
- - - -
TOTAL RECOMMENDED $740,671 $1,073,377 $187,885
2,965,376
kWh
$346,520
-
MMBtu
$235,989
-
MMBtu
$(-17,753.0) $(-11,970.0)
TOTAL IMPLEMENTED $333,287 $184,297 $29,791
470,200
kWh
$304,636
-
MMBtu
- $(-1,140.0) -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Other Energy Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs