Assessment Year | 2024 |
---|---|
Principal Product | Medical Services |
NAICS | 622110: General Medical and Surgical Hospitals |
SIC | 8062: General Medical and Surgical Hospitals |
Sales Range | $1 M to 5M |
# of Employees | 6,700 |
Plant Area |
100,000
ft2
|
Annual Production | 1
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $2,228,458 | 38,043,420 |
kWh
|
$0.059 | |
Electricity Demand | $1,307,515 | 92,419 |
kW-mo/yr
|
$14.15 | |
Electricity Fees | $202,848 | - |
|
- | |
Natural Gas | $400,652 | 61,753 |
MMBtu
|
$6.49 | |
Waste Disposal Costs | |||||
Water Usage | $801,470 | 71,190 |
Tgal
|
$11.26 | |
TOTAL YEARLY COSTS | $4,940,943 | ||||
RECOMMENDED SAVINGS* | $337,682 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $218,122 | $1,758,568 |
$204,745
3,542,306
kWh
|
$47,577
-
kW-mo/yr
|
- | $(-34,200.0) | |
02 | 2.1224: Replace boiler | $56,229 | $300,000 | - | - |
$56,229
-
MMBtu
|
- | |
03 | 2.2511: Insulate bare equipment | $50,126 | $154,154 |
$26,781
463,334
kWh
|
$23,345
-
kW-mo/yr
|
- | - | |
04 | 4.611: Begin a practice of predictive / preventative maintenance | $11,158 | $14,100 |
$11,158
109,715
kWh
|
- | - | - | |
05 | 2.7132: Install timers on light switches in little used areas | $1,756 | $1,363 |
$1,756
17,259
kWh
|
- | - | - | |
06 | 2.6211: Conserve energy by efficient use of vending machines | $291 | $140 |
$264
2,595
kWh
|
$27
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $337,682 | $2,228,325 |
$244,704
4,135,209
kWh
|
$70,949
-
kW-mo/yr
|
$56,229
-
MMBtu
|
$(-34,200.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs