ITAC Assessment: WV0446
ITAC logo
ITAC Assessment: WV0446
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Flavors
NAICS 311930: Flavoring Syrup and Concentrate Manufacturing
SIC 2087: Flavoring Extracts and Flavoring Syrups, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 200
Plant Area 110,000
ft2
Annual Production 10,000,000
lb
Production Hrs. Annual 8,568
hrs
Location (State) Maryland

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $924,720 9,659,300
kWh
Electricity Demand $45,961 19,071
kW-mo/yr
Natural Gas $414,297 59,431
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $270,250 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $39,724

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat $147,469 $548,000 $200,132
2,090,952
kWh
$7,056
-
kW-mo/yr
$(-59,719.0)
-
MMBtu
-
02 2.4322: Use or replace with energy efficient substitutes $21,144 $70,000 $20,423
213,343
kWh
$721
-
kW-mo/yr
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $20,208 $21,000 $20,208
211,098
kWh
- - -
04 2.4156: Establish a preventative maintenance program $16,273 $1,000 $16,597
173,369
kWh
$586
-
kW-mo/yr
- $(-910.0)
05 2.4312: Improve lubrication practices $10,748 $2,034 $10,382
108,450
kWh
$366
-
kW-mo/yr
- -
06 2.1221: Replace obsolete burners with more efficient ones $9,842 $9,500 - - $9,842
-
MMBtu
-
07 2.2414: Use waste heat from hot flue gases to preheat $8,197 $32,125 - - $8,197
-
MMBtu
-
08 2.1233: Analyze flue gas for proper air/fuel ratio $6,963 $2,500 - - $7,068
-
MMBtu
$(-105.0)
09 2.4151: Develop a repair/replace policy $6,712 $5,683 $8,511
88,907
kWh
$301
-
kW-mo/yr
- $(-2,100.0)
10 2.4239: Eliminate or reduce compressed air usage $6,393 $423 $6,176
64,517
kWh
$217
-
kW-mo/yr
- -
11 2.2113: Repair or replace steam traps $3,610 $4,438 - - $4,182
-
MMBtu
$(-572.0)
12 2.4231: Reduce the pressure of compressed air to the minimum required $2,862 $1,070 $2,766
28,893
kWh
$96
-
kW-mo/yr
- -
13 2.2136: Install / repair insulation on steam lines $2,788 $1,351 - - $2,788
-
MMBtu
-
14 2.3131: Reschedule plant operations or reduce load to avoid peaks $2,403 $5,700 - $2,403
-
kW-mo/yr
- -
15 2.2625: Chill water to the highest temperature possible $2,151 $70 $2,079
21,715
kWh
$72
-
kW-mo/yr
- -
16 2.4221: Install compressor air intakes in coolest locations $1,334 $1,625 $1,288
13,456
kWh
$46
-
kW-mo/yr
- -
17 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,153 $475 $1,114
11,633
kWh
$39
-
kW-mo/yr
- -
TOTAL RECOMMENDED $270,250 $706,994 $289,676
3,026,333
kWh
$11,903
-
kW-mo/yr
$(-27,642.0)
-
MMBtu
$(-3,687.0)
TOTAL IMPLEMENTED $39,724 $15,236 $31,067
324,517
kWh
$1,094
-
kW-mo/yr
$11,250
-
MMBtu
$(-3,687.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs