ITAC Assessment: WV0445
ITAC logo
ITAC Assessment: WV0445
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Vinyl Siding
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 175
Plant Area 165,000
ft2
Annual Production 60,000,000
lb
Production Hrs. Annual 4,368
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $511,119 12,824,519
kWh
Electricity Demand $359,203 26,418
kW-mo/yr
Natural Gas $55,733 6,331
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $85,060 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $34,190

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.4224: Upgrade controls on compressors $10,833 $29,500 $5,597
140,640
kWh
$5,236
-
kW-mo/yr
- -
02 2.4157: Establish a predictive maintenance program $9,398 $1,000 $7,728
194,177
kWh
$4,230
-
kW-mo/yr
- $(-2,560.0)
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $9,071 $15,050 $9,071
227,911
kWh
- - -
04 2.3132: Recharge batteries on during off-peak demand periods $10,469 - - $9,629
-
kW-mo/yr
- $840
05 2.7142: Utilize higher efficiency lamps and/or ballasts $8,693 $40,964 $5,619
141,186
kWh
$3,074
-
kW-mo/yr
- -
06 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle $8,421 $415 - - $8,421
-
MMBtu
-
07 2.4155: Standardize motor inventory $8,227 $920 $6,507
155,965
kWh
$3,400
-
kW-mo/yr
- $(-1,680.0)
08 2.7142: Utilize higher efficiency lamps and/or ballasts $4,321 $8,880 $2,621
65,859
kWh
$1,700
-
kW-mo/yr
- -
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,036 $4,975 $4,036
101,417
kWh
- - -
10 2.2511: Insulate bare equipment $3,234 $4,181 $2,089
52,409
kWh
$1,145
-
kW-mo/yr
- -
11 2.4312: Improve lubrication practices $2,929 $2,741 $1,862
46,796
kWh
$1,067
-
kW-mo/yr
- -
12 2.4231: Reduce the pressure of compressed air to the minimum required $1,961 $105 $1,267
31,841
kWh
$694
-
kW-mo/yr
- -
13 2.4221: Install compressor air intakes in coolest locations $1,693 $2,745 $1,095
27,514
kWh
$598
-
kW-mo/yr
- -
14 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,412 $543 $909
22,847
kWh
$503
-
kW-mo/yr
- -
15 2.4239: Eliminate or reduce compressed air usage $188 $423 $188
4,727
kWh
- - -
16 2.4235: Remove or close off unneeded compressed air lines $174 $555 $174
4,366
kWh
- - -
TOTAL RECOMMENDED $85,060 $112,997 $48,763
1,217,655
kWh
$31,276
-
kW-mo/yr
$8,421
-
MMBtu
$(-3,400.0)
TOTAL IMPLEMENTED $34,190 $46,208 $9,884
248,283
kWh
$15,045
-
kW-mo/yr
$8,421
-
MMBtu
$840
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs