ITAC Assessment: WV0439
ITAC logo
ITAC Assessment: WV0439
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product food grade plastic containers and covers
NAICS 326111: Plastics Bag and Pouch Manufacturing
SIC 2673: Plastics, Foil, and Coated Paper Bags
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 180,000
ft2
Annual Production 90,000,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,273,079 32,870,604
kWh
Electricity Demand $793,166 57,162
kW-mo/yr
Natural Gas $103,709 19,728
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $277,652 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $73,666

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $67,687 $83,338 $49,213
1,270,674
kWh
$18,474
-
kW-mo/yr
- -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $48,688 $48,160 $48,688
1,257,106
kWh
- - -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $47,442 $26,920 - $47,442
-
kW-mo/yr
- -
04 2.4151: Develop a repair/replace policy $23,664 $1,202 $16,641
429,657
kWh
$8,175
-
kW-mo/yr
- $(-1,152.0)
05 2.4224: Upgrade controls on compressors $22,385 $30,600 $15,014
387,659
kWh
$7,371
-
kW-mo/yr
- -
06 2.4157: Establish a predictive maintenance program $20,648 $4,000 $14,477
373,801
kWh
$7,107
-
kW-mo/yr
- $(-936.0)
07 2.4312: Improve lubrication practices $12,205 $8,311 $8,186
211,367
kWh
$4,019
-
kW-mo/yr
- -
08 2.4231: Reduce the pressure of compressed air to the minimum required $9,735 $96 $6,529
168,571
kWh
$3,206
-
kW-mo/yr
- -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $9,194 $468 $6,168
159,257
kWh
$3,026
-
kW-mo/yr
- -
10 2.2625: Chill water to the highest temperature possible $4,477 $144 $3,006
77,616
kWh
$1,471
-
kW-mo/yr
- -
11 2.2511: Insulate bare equipment $4,234 $972 - - $4,234
-
MMBtu
-
12 2.7241: Install outside air damper / economizer on hvac unit $3,745 $7,360 $3,745
96,690
kWh
- - -
13 2.2414: Use waste heat from hot flue gases to preheat $1,536 $9,580 - - $1,536
-
MMBtu
-
14 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,083 $3,000 $722
18,630
kWh
$361
-
kW-mo/yr
- -
15 2.1233: Analyze flue gas for proper air/fuel ratio $631 $1,000 - - $631
-
MMBtu
-
16 2.7135: Install occupancy sensors $298 $518 $298
7,705
kWh
- - -
TOTAL RECOMMENDED $277,652 $225,669 $172,687
4,458,733
kWh
$100,652
-
kW-mo/yr
$6,401
-
MMBtu
$(-2,088.0)
TOTAL IMPLEMENTED $73,666 $10,882 $47,543
1,227,532
kWh
$23,346
-
kW-mo/yr
$4,865
-
MMBtu
$(-2,088.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs