ITAC Assessment: WV0396
ITAC logo
ITAC Assessment: WV0396
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Recycled paper board
NAICS 322130: Paperboard Mills
SIC 2631: Paperboard Mills
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area 160,000
ft2
Annual Production 35,000
ton
Production Hrs. Annual 7,200
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $517,419 18,874,575
kWh
Electricity Demand $441,292 36,732
kW-mo/yr
Coal $918,051 215,964
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $678,547 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $102,580

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Coal Savings Personnel Changes Savings
01 4.132: Purchase new equipment to reduce material use / cost $404,150 $744,800 - - $404,150
-
MMBtu
-
02 2.2163: Use minimum steam operating pressure $80,973 $54,000 $1,858
67,800
kWh
$889
-
kW-mo/yr
$78,226
-
MMBtu
-
03 2.3321: Use steam pressure reduction to generate power $72,044 $295,680 $21,314
2,534,400
kWh
$50,730
-
kW-mo/yr
- -
04 2.1233: Analyze flue gas for proper air/fuel ratio $69,637 $1,000 - - $69,675
-
MMBtu
$(-38.0)
05 2.2136: Install / repair insulation on steam lines $10,128 $3,390 - - $10,128
-
MMBtu
-
06 2.4151: Develop a repair/replace policy $9,954 $1,094 $8,538
209,931
kWh
$1,566
-
kW-mo/yr
- $(-150.0)
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $9,556 $10,996 $5,521
201,416
kWh
$4,035
-
kW-mo/yr
- -
08 2.4157: Establish a predictive maintenance program $8,609 $1,000 $5,176
188,845
kWh
$3,783
-
kW-mo/yr
- $(-350.0)
09 2.3212: Optimize plant power factor $7,614 $28,000 $7,614
-
kWh
- - -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,796 $263 $1,039
37,921
kWh
$757
-
kW-mo/yr
- -
11 2.4221: Install compressor air intakes in coolest locations $1,630 $445 $945
34,470
kWh
$685
-
kW-mo/yr
- -
12 2.4231: Reduce the pressure of compressed air to the minimum required $846 $50 $486
17,745
kWh
$360
-
kW-mo/yr
- -
13 2.7142: Utilize higher efficiency lamps and/or ballasts $829 - $481
17,554
kWh
$348
-
kW-mo/yr
- -
14 2.7241: Install outside air damper / economizer on hvac unit $781 $575 $241
8,790
kWh
$540
-
kW-mo/yr
- -
TOTAL RECOMMENDED $678,547 $1,141,293 $53,213
3,318,872
kWh
$63,693
-
kW-mo/yr
$562,179
-
MMBtu
$(-538.0)
TOTAL IMPLEMENTED $102,580 $7,372 $15,961
480,786
kWh
$7,354
-
kW-mo/yr
$79,803
-
MMBtu
$(-538.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Coal Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs