ITAC Assessment: WV0387
ITAC logo
ITAC Assessment: WV0387
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Bed Pillows
NAICS 314120: Curtain and Linen Mills
SIC 2392: House furnishing, Except Curtains and Draperies
Sales Range $50
M
to 100
M
# of Employees 237
Plant Area 190,000
ft2
Annual Production 3,500,000
lb
Production Hrs. Annual 4,680
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $224,789 2,784,600
kWh
Electricity Demand $41,017 6,167
kW-mo/yr
Electricity Fees $413 -
Natural Gas $104,347 7,411
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $81,634 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $58,197

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $43,474 $56,368 $35,893
444,601
kWh
$7,581
-
kW-mo/yr
-
02 2.4239: Eliminate or reduce compressed air usage $7,123 $12,560 $5,879
72,823
kWh
$1,244
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $5,978 - $4,936
61,140
kWh
$1,042
-
kW-mo/yr
-
04 2.2437: Recover waste heat from equipment $4,801 $1,480 - - $4,801
-
MMBtu
05 2.7111: Reduce illumination to minimum necessary levels $4,208 $47 $3,476
43,056
kWh
$732
-
kW-mo/yr
-
06 2.3212: Optimize plant power factor $3,260 $4,450 $3,260
-
kWh
- -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,818 $148 $2,327
28,838
kWh
$491
-
kW-mo/yr
-
08 2.4151: Develop a repair/replace policy $2,515 $651 $2,023
27,140
kWh
$492
-
kW-mo/yr
-
09 2.7241: Install outside air damper / economizer on hvac unit $2,292 $3,840 $1,703
21,096
kWh
$589
-
kW-mo/yr
-
10 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,892 - $1,559
19,314
kWh
$333
-
kW-mo/yr
-
11 2.4221: Install compressor air intakes in coolest locations $1,753 $460 $1,447
17,921
kWh
$306
-
kW-mo/yr
-
12 2.4231: Reduce the pressure of compressed air to the minimum required $1,520 $28 $1,255
15,552
kWh
$265
-
kW-mo/yr
-
TOTAL RECOMMENDED $81,634 $80,032 $63,758
751,481
kWh
$13,075
-
kW-mo/yr
$4,801
-
MMBtu
TOTAL IMPLEMENTED $58,197 $57,195 $47,993
596,585
kWh
$10,204
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs