ITAC Assessment: WV0380
ITAC logo
ITAC Assessment: WV0380
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Pipe plugs and Reducer pushings
NAICS 332721: Precision Turned Product Manufacturing
SIC 3451: Screw Machine Products
Sales Range $10
M
to 50
M
# of Employees 128
Plant Area 192,000
ft2
Annual Production 60,000,000
pieces
Production Hrs. Annual 5,460
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $127,318 2,133,000
kWh
Electricity Demand $64,210 5,245
kW-mo/yr
Natural Gas $41,135 3,577
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $73,567 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $31,850

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.3212: Optimize plant power factor $18,045 $7,420 $18,045
-
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $14,037 $8,850 $9,680
162,167
kWh
$4,357
-
kW-mo/yr
-
03 2.1233: Analyze flue gas for proper air/fuel ratio $7,429 $3,300 - - $7,429
-
MMBtu
04 2.3512: De-energize excess transformer capacity $6,055 $4,950 $2,614
43,800
kWh
$3,441
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $5,310 - $3,658
61,283
kWh
$1,652
-
kW-mo/yr
-
06 2.2437: Recover waste heat from equipment $4,106 $1,120 - - $4,106
-
MMBtu
07 2.4157: Establish a predictive maintenance program $3,939 $1,690 $2,715
45,479
kWh
$1,224
-
kW-mo/yr
-
08 2.7232: Replace existing hvac unit with high efficiency model $3,853 $13,200 - - $3,853
-
MMBtu
09 2.4151: Develop a repair/replace policy $2,626 $1,018 $1,810
30,321
kWh
$816
-
kW-mo/yr
-
10 2.4231: Reduce the pressure of compressed air to the minimum required $2,058 $30 $1,422
23,830
kWh
$636
-
kW-mo/yr
-
11 2.4239: Eliminate or reduce compressed air usage $1,989 $1,550 $1,536
25,740
kWh
$453
-
kW-mo/yr
-
12 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,891 - $1,303
21,846
kWh
$588
-
kW-mo/yr
-
13 2.4221: Install compressor air intakes in coolest locations $1,422 $225 $980
16,417
kWh
$442
-
kW-mo/yr
-
14 2.1243: Use heat from boiler blowdown to preheat boiler feed water $807 $4,400 - - $807
-
MMBtu
TOTAL RECOMMENDED $73,567 $47,753 $43,763
430,883
kWh
$13,609
-
kW-mo/yr
$16,195
-
MMBtu
TOTAL IMPLEMENTED $31,850 $13,138 $22,124
370,666
kWh
$9,726
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs