ITAC Assessment: OK0036
ITAC logo
ITAC Assessment: OK0036
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product CONCRETE BLOCKS ETC.
NAICS
n/a
SIC 3271: Concrete Block and Brick
Sales Range $5
M
to 10
M
# of Employees 190
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 3,000
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $72,085 1,370,457
kWh
Natural Gas $128,888 50,502
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,148 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,148

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $4,397 $600 - $4,397
-
MMBtu
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,757 $140 $3,757
75,909
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $6,447 $8,375 $6,447
105,510
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,547 $675 $1,547
31,360
kWh
-
TOTAL RECOMMENDED $16,148 $9,790 $11,751
212,779
kWh
$4,397
-
MMBtu
TOTAL IMPLEMENTED $16,148 $9,790 $11,751
212,779
kWh
$4,397
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs