ITAC Assessment: WV0375
ITAC logo
ITAC Assessment: WV0375
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Copper sheet and bus bars
NAICS 331410: Nonferrous Metal (except Aluminum) Smelting and Refining
SIC 3366: Copper Foundries
Sales Range $100
M
to 500
M
# of Employees 100
Plant Area 287,000
ft2
Annual Production 108,625
ton
Production Hrs. Annual 8,568
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,475,087 43,496,231
kWh
Electricity Demand $683,263 86,066
kW-mo/yr
Electricity Fees $288 -
Natural Gas $3,943,229 440,917
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $2,395,286 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $845,087

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings Water Consumption Savings Increase in Production Savings
01 2.2424: Use heat in flue gases to preheat products or materials $1,181,139 $1,147,130 - - $81,139
-
MMBtu
- - - $1,100,000
02 2.1133: Adjust burners for efficient operation $396,584 $183,040 - - $396,584
-
MMBtu
- - - -
03 2.2414: Use waste heat from hot flue gases to preheat $250,246 $168,224 - - $250,246
-
MMBtu
- - - -
04 2.2421: Install waste heat boiler to provide direct power $97,283 $434,500 $76,147
1,338,260
kWh
$21,136
-
kW-mo/yr
- - - - -
05 2.2121: Increase amount of condensate returned $84,029 $50,400 - - $69,312
-
MMBtu
$4,415
-
gal
- $10,302
-
Tgal
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $82,382 $83,840 $68,916
1,211,172
kWh
$13,466
-
kW-mo/yr
- - - - -
07 2.7231: Use radiant heater for spot heating $23,729 $37,200 $54,846
963,900
kWh
$7,182
-
kW-mo/yr
$(-38,299.0)
-
MMBtu
- - - -
08 2.2426: Use waste heat from flue gases to heat space conditioning air $59,537 $62,535 $52,645
925,224
kWh
$6,892
-
kW-mo/yr
- - - - -
09 2.3191: Use demand controller or load shedder $57,494 $25,520 - $57,494
-
kW-mo/yr
- - - - -
10 2.2437: Recover waste heat from equipment $34,143 $15,525 $30,189
530,560
kWh
$3,954
-
kW-mo/yr
- - - - -
11 2.2515: Use optimum thickness insulation $33,427 $6,567 - - $33,427
-
MMBtu
- - - -
12 2.4151: Develop a repair/replace policy $32,477 $1,338 $28,713
504,621
kWh
$3,764
-
kW-mo/yr
- - - - -
13 2.1233: Analyze flue gas for proper air/fuel ratio $29,817 $2,000 - - $29,895
-
MMBtu
- $(-78.0) - -
14 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $12,983 $772 $11,482
201,787
kWh
$1,501
-
kW-mo/yr
- - - - -
15 2.4224: Upgrade controls on compressors $7,595 $4,650 $5,361
94,224
kWh
$2,234
-
kW-mo/yr
- - - - -
16 2.4231: Reduce the pressure of compressed air to the minimum required $4,374 $52 $3,866
67,943
kWh
$508
-
kW-mo/yr
- - - - -
17 2.4221: Install compressor air intakes in coolest locations $2,975 $652 $2,634
46,298
kWh
$341
-
kW-mo/yr
- - - - -
18 2.7142: Utilize higher efficiency lamps and/or ballasts $2,797 $10,125 $1,765
31,026
kWh
$1,032
-
kW-mo/yr
- - - - -
19 2.3131: Reschedule plant operations or reduce load to avoid peaks $2,275 - - $4,675
-
kW-mo/yr
- - $(-2,400.0) - -
TOTAL RECOMMENDED $2,395,286 $2,234,070 $336,564
5,915,015
kWh
$124,179
-
kW-mo/yr
$822,304
-
MMBtu
$4,415
-
gal
$(-2,478.0) $10,302
-
Tgal
$1,100,000
TOTAL IMPLEMENTED $845,087 $455,958 $114,742
2,016,549
kWh
$20,271
-
kW-mo/yr
$710,152
-
MMBtu
- $(-78.0) - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings Water Consumption Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs