ITAC Assessment: WV0370
ITAC logo
ITAC Assessment: WV0370
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product printed material
NAICS 323111: Commercial Printing (except Screen and Books)
SIC 2759: Commercial Printing, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 900
Plant Area 1,600,000
ft2
Annual Production 165,700,000,000
units
Production Hrs. Annual 8,760
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,482,179 106,798,943
kWh
Electricity Demand $1,384,046 192,704
kW-mo/yr
Natural Gas $5,671,955 573,353
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,074,253 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,014,768

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.2113: Repair or replace steam traps $544,142 $5,500 - - $554,542
-
MMBtu
$(-10,400.0)
02 2.2449: Recover heat from exhausted steam, hot air or hot water $416,253 $371,400 $(-55,180.0)
(-2,378,435)
kWh
$(-23,393.0)
-
kW-mo/yr
$494,826
-
MMBtu
-
03 2.2628: Utilize a less expensive cooling method $44,891 $54,835 $37,892
1,633,288
kWh
$16,062
-
kW-mo/yr
- $(-9,063.0)
04 2.4151: Develop a repair/replace policy $32,574 $3,560 $23,045
993,344
kWh
$9,769
-
kW-mo/yr
- $(-240.0)
05 2.6218: Turn off equipment when not in use $21,799 $8,800 $15,309
659,854
kWh
$6,490
-
kW-mo/yr
- -
06 2.4221: Install compressor air intakes in coolest locations $14,594 $2,720 $11,363
489,789
kWh
$3,231
-
kW-mo/yr
- -
TOTAL RECOMMENDED $1,074,253 $446,815 $32,429
1,397,840
kWh
$12,159
-
kW-mo/yr
$1,049,368
-
MMBtu
$(-19,703.0)
TOTAL IMPLEMENTED $1,014,768 $389,260 $(-16,826.0)
(-725,237)
kWh
$(-7,134.0)
-
kW-mo/yr
$1,049,368
-
MMBtu
$(-10,640.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs