Assessment Year | 2008 |
---|---|
Principal Product | printed material |
NAICS | 323111: Commercial Printing (except Screen and Books) |
SIC | 2759: Commercial Printing, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 900 |
Plant Area |
1,600,000
ft2
|
Annual Production | 165,700,000,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,482,179 | 106,798,943 |
kWh
|
$0.023 |
Electricity Demand | $1,384,046 | 192,704 |
kW-mo/yr
|
$7.18 |
Natural Gas | $5,671,955 | 573,353 |
MMBtu
|
$9.89 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,074,253 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,014,768 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2113: Repair or replace steam traps | $544,142 | $5,500 | - | - |
$554,542
-
MMBtu
|
$(-10,400.0) | |
02 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $416,253 | $371,400 |
$(-55,180.0)
(-2,378,435)
kWh
|
$(-23,393.0)
-
kW-mo/yr
|
$494,826
-
MMBtu
|
- | |
03 | 2.2628: Utilize a less expensive cooling method | $44,891 | $54,835 |
$37,892
1,633,288
kWh
|
$16,062
-
kW-mo/yr
|
- | $(-9,063.0) | |
04 | 2.4151: Develop a repair/replace policy | $32,574 | $3,560 |
$23,045
993,344
kWh
|
$9,769
-
kW-mo/yr
|
- | $(-240.0) | |
05 | 2.6218: Turn off equipment when not in use | $21,799 | $8,800 |
$15,309
659,854
kWh
|
$6,490
-
kW-mo/yr
|
- | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $14,594 | $2,720 |
$11,363
489,789
kWh
|
$3,231
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $1,074,253 | $446,815 |
$32,429
1,397,840
kWh
|
$12,159
-
kW-mo/yr
|
$1,049,368
-
MMBtu
|
$(-19,703.0) | ||
TOTAL IMPLEMENTED | $1,014,768 | $389,260 |
$(-16,826.0)
(-725,237)
kWh
|
$(-7,134.0)
-
kW-mo/yr
|
$1,049,368
-
MMBtu
|
$(-10,640.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs