ITAC Assessment: WV0358
ITAC logo
ITAC Assessment: WV0358
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Polyethylene containment tanks
NAICS 332420: Metal Tank (Heavy Gauge) Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 27
Plant Area 25,000
ft2
Annual Production 24,000
pieces
Production Hrs. Annual 8,568
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $81,216 1,467,000
kWh
Electricity Demand $3,338 3,338
kW-mo/yr
Electricity Fees $194 -
Natural Gas $612,376 51,082
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $178,476 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $55,578

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.1116: Improve combustion control capability $91,739 $34,400 - - $95,105
-
MMBtu
$(-3,366.0)
02 2.2414: Use waste heat from hot flue gases to preheat $27,409 $34,100 - - $27,409
-
MMBtu
-
03 2.1131: Repair faulty insulation in furnaces, boilers, etc $20,287 $6,050 - - $20,287
-
MMBtu
-
04 2.1113: Reduce combustion air flow to optimum $24,675 $15,300 - - $24,939
-
MMBtu
$(-264.0)
05 2.7142: Utilize higher efficiency lamps and/or ballasts $4,775 $8,600 $4,657
84,138
kWh
$118
-
kW-mo/yr
- -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,908 $5,830 $2,860
51,663
kWh
$48
-
kW-mo/yr
- -
07 2.4157: Establish a predictive maintenance program $1,651 $1,000 $1,681
30,360
kWh
$43
-
kW-mo/yr
- $(-73.0)
08 2.7142: Utilize higher efficiency lamps and/or ballasts $1,029 - $1,004
18,130
kWh
$25
-
kW-mo/yr
- -
09 2.4151: Develop a repair/replace policy $1,016 $555 $1,120
20,240
kWh
$28
-
kW-mo/yr
- $(-132.0)
10 2.4231: Reduce the pressure of compressed air to the minimum required $998 $1,555 $973
17,512
kWh
$25
-
kW-mo/yr
- -
11 2.7135: Install occupancy sensors $679 $2,103 $626
11,303
kWh
$53
-
kW-mo/yr
- -
12 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $468 $78 $456
8,245
kWh
$12
-
kW-mo/yr
- -
13 2.4221: Install compressor air intakes in coolest locations $432 $119 $421
7,611
kWh
$11
-
kW-mo/yr
- -
14 2.4231: Reduce the pressure of compressed air to the minimum required $410 $22 $403
7,284
kWh
$7
-
kW-mo/yr
- -
TOTAL RECOMMENDED $178,476 $109,712 $14,201
256,486
kWh
$370
-
kW-mo/yr
$167,740
-
MMBtu
$(-3,835.0)
TOTAL IMPLEMENTED $55,578 $35,241 $10,517
189,928
kWh
$304
-
kW-mo/yr
$45,226
-
MMBtu
$(-469.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs