ITAC Assessment: WV0355
ITAC logo
ITAC Assessment: WV0355
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product crowns and closures
NAICS 332119: Metal Crown, Closure, and Other Metal Stamping (except Automotive)
SIC 3466: Crowns and Closures
Sales Range $50
M
to 100
M
# of Employees 132
Plant Area 276,021
ft2
Annual Production 330,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $372,760 15,234,666
kWh
Electricity Demand $278,805 32,420
kW-mo/yr
Electricity Fees $9,622 -
Natural Gas $1,299,006 97,768
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $519,944 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $151,662

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7231: Use radiant heater for spot heating $187,442 $70,000 - - $187,442
-
MMBtu
- -
02 2.2511: Insulate bare equipment $99,024 $30,573 - - $99,024
-
MMBtu
- -
03 2.1113: Reduce combustion air flow to optimum $63,700 $65,000 - - $63,805
-
MMBtu
$(-105.0) -
04 2.2437: Recover waste heat from equipment $47,113 $11,460 - - $47,113
-
MMBtu
- -
05 2.4239: Eliminate or reduce compressed air usage $24,887 $25,000 $17,130
700,058
kWh
$7,757
-
kW-mo/yr
- - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $17,682 $6,140 $13,272
542,387
kWh
$8,970
-
kW-mo/yr
- $(-560.0) $(-4,000.0)
07 2.2414: Use waste heat from hot flue gases to preheat $17,171 $10,940 - - $17,171
-
MMBtu
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $14,654 $39,137 $9,649
394,311
kWh
$5,005
-
kW-mo/yr
- - -
09 2.4221: Install compressor air intakes in coolest locations $9,370 $5,220 $6,446
263,525
kWh
$2,924
-
kW-mo/yr
- - -
10 2.1233: Analyze flue gas for proper air/fuel ratio $8,946 $4,000 - - $9,051
-
MMBtu
$(-105.0) -
11 2.4157: Establish a predictive maintenance program $7,728 $3,500 $4,987
203,838
kWh
$3,371
-
kW-mo/yr
- $(-630.0) -
12 2.4314: Use synthetic lubricant $5,378 $2,150 $3,211
131,241
kWh
$2,167
-
kW-mo/yr
- - -
13 2.4151: Develop a repair/replace policy $5,152 $1,973 $3,325
135,891
kWh
$2,247
-
kW-mo/yr
- $(-420.0) -
14 3.6124: Burn waste oil for heat $4,426 $3,700 - - $4,426
-
MMBtu
- -
15 2.7135: Install occupancy sensors $2,673 $2,890 $2,673
109,250
kWh
- - - -
16 2.7142: Utilize higher efficiency lamps and/or ballasts $2,450 - $1,461
59,704
kWh
$989
-
kW-mo/yr
- - -
17 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,148 $2,700 $1,477
60,283
kWh
$671
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $519,944 $284,383 $63,631
2,600,488
kWh
$34,101
-
kW-mo/yr
$428,032
-
MMBtu
$(-1,820.0) $(-4,000.0)
TOTAL IMPLEMENTED $151,662 $152,060 $55,433
2,265,409
kWh
$28,563
-
kW-mo/yr
$72,856
-
MMBtu
$(-1,190.0) $(-4,000.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs