ITAC Assessment: WV0353
ITAC logo
ITAC Assessment: WV0353
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Pork and beef patties
NAICS 311612: Meat Processed from Carcasses
SIC 2013: Sausages and Other Prepared Meat Products
Sales Range $50
M
to 100
M
# of Employees 270
Plant Area 65,000
ft2
Annual Production 50,000,000
lb
Production Hrs. Annual 4,160
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $335,582 14,407,296
kWh
Electricity Demand $268,559 31,594
kW-mo/yr
Electricity Fees $6,905 -
Natural Gas $1,726,492 133,084
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $441,921 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $70,692

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings One-time Revenue or Avoided Cost Savings
01 2.2437: Recover waste heat from equipment $187,287 $59,000 - - - $187,287
-
MMBtu
- - - -
02 2.1221: Replace obsolete burners with more efficient ones $133,786 $400,000 - - - $133,786
-
MMBtu
- - - -
03 2.2113: Repair or replace steam traps $48,101 $4,000 - - - $48,261
-
MMBtu
$(-160.0) - - -
04 2.2121: Increase amount of condensate returned $24,450 $50,000 - - - $22,360
-
MMBtu
- $627 $1,463
-
Tgal
-
05 2.2414: Use waste heat from hot flue gases to preheat $13,839 $2,960 - - - $13,839
-
MMBtu
- - - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,776 $300 $6,574
282,376
kWh
$2,202
-
kW-mo/yr
- - - - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $7,148 $19,000 $3,705
159,185
kWh
$3,443
-
kW-mo/yr
- - - - - -
08 2.2437: Recover waste heat from equipment $5,712 $400 $743
31,796
kWh
$144
-
kW-mo/yr
- $4,825
-
MMBtu
- - - -
09 2.3212: Optimize plant power factor $4,799 $17,500 - - $4,799 - - - - -
10 2.4231: Reduce the pressure of compressed air to the minimum required $3,101 $3,500 $2,321
99,729
kWh
$780
-
kW-mo/yr
- - - - - -
11 2.4151: Develop a repair/replace policy $1,883 $400 $1,438
61,823
kWh
$1,405
-
kW-mo/yr
- - $(-960.0) - - -
12 2.4221: Install compressor air intakes in coolest locations $1,356 $200 $1,016
43,579
kWh
$340
-
kW-mo/yr
- - - - - -
13 2.4235: Remove or close off unneeded compressed air lines $887 $200 $887
38,227
kWh
- - - - - - -
14 2.7142: Utilize higher efficiency lamps and/or ballasts $796 $3,000 $552
23,729
kWh
- - - - - - $244
TOTAL RECOMMENDED $441,921 $560,460 $17,236
740,444
kWh
$8,314
-
kW-mo/yr
$4,799 $410,358
-
MMBtu
$(-1,120.0) $627 $1,463
-
Tgal
$244
TOTAL IMPLEMENTED $70,692 $30,400 $15,477
665,069
kWh
$7,830
-
kW-mo/yr
- $48,261
-
MMBtu
$(-1,120.0) - - $244
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs