Assessment Year | 2006 |
---|---|
Principal Product | Pork and beef patties |
NAICS | 311612: Meat Processed from Carcasses |
SIC | 2013: Sausages and Other Prepared Meat Products |
Sales Range | $50 M to 100M |
# of Employees | 270 |
Plant Area |
65,000
ft2
|
Annual Production | 50,000,000
lb
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $335,582 | 14,407,296 |
kWh
|
$0.023 |
Electricity Demand | $268,559 | 31,594 |
kW-mo/yr
|
$8.50 |
Electricity Fees | $6,905 | - |
|
- |
Natural Gas | $1,726,492 | 133,084 |
MMBtu
|
$12.97 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $441,921 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $70,692 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $187,287 | $59,000 | - | - | - |
$187,287
-
MMBtu
|
- | - | - | - | |
02 | 2.1221: Replace obsolete burners with more efficient ones | $133,786 | $400,000 | - | - | - |
$133,786
-
MMBtu
|
- | - | - | - | |
03 | 2.2113: Repair or replace steam traps | $48,101 | $4,000 | - | - | - |
$48,261
-
MMBtu
|
$(-160.0) | - | - | - | |
04 | 2.2121: Increase amount of condensate returned | $24,450 | $50,000 | - | - | - |
$22,360
-
MMBtu
|
- | $627 |
$1,463
-
Tgal
|
- | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $13,839 | $2,960 | - | - | - |
$13,839
-
MMBtu
|
- | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,776 | $300 |
$6,574
282,376
kWh
|
$2,202
-
kW-mo/yr
|
- | - | - | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,148 | $19,000 |
$3,705
159,185
kWh
|
$3,443
-
kW-mo/yr
|
- | - | - | - | - | - | |
08 | 2.2437: Recover waste heat from equipment | $5,712 | $400 |
$743
31,796
kWh
|
$144
-
kW-mo/yr
|
- |
$4,825
-
MMBtu
|
- | - | - | - | |
09 | 2.3212: Optimize plant power factor | $4,799 | $17,500 | - | - | $4,799 | - | - | - | - | - | |
10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,101 | $3,500 |
$2,321
99,729
kWh
|
$780
-
kW-mo/yr
|
- | - | - | - | - | - | |
11 | 2.4151: Develop a repair/replace policy | $1,883 | $400 |
$1,438
61,823
kWh
|
$1,405
-
kW-mo/yr
|
- | - | $(-960.0) | - | - | - | |
12 | 2.4221: Install compressor air intakes in coolest locations | $1,356 | $200 |
$1,016
43,579
kWh
|
$340
-
kW-mo/yr
|
- | - | - | - | - | - | |
13 | 2.4235: Remove or close off unneeded compressed air lines | $887 | $200 |
$887
38,227
kWh
|
- | - | - | - | - | - | - | |
14 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $796 | $3,000 |
$552
23,729
kWh
|
- | - | - | - | - | - | $244 | |
TOTAL RECOMMENDED | $441,921 | $560,460 |
$17,236
740,444
kWh
|
$8,314
-
kW-mo/yr
|
$4,799 |
$410,358
-
MMBtu
|
$(-1,120.0) | $627 |
$1,463
-
Tgal
|
$244 | ||
TOTAL IMPLEMENTED | $70,692 | $30,400 |
$15,477
665,069
kWh
|
$7,830
-
kW-mo/yr
|
- |
$48,261
-
MMBtu
|
$(-1,120.0) | - | - | $244 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs