Assessment Year | 2006 |
---|---|
Principal Product | Micro Toner and Ribbons |
NAICS | 325992: Photographic Film, Paper, Plate, and Chemical Manufacturing |
SIC | 3861: Photographic Equipment and Supplies |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
88,000
ft2
|
Annual Production | 790,000
lb
|
Production Hrs. Annual | 3,016
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $86,605 | 3,095,240 |
kWh
|
$0.028 |
Electricity Demand | $99,487 | 12,267 |
kW-mo/yr
|
$8.11 |
Natural Gas | $86,925 | 7,983 |
MMBtu
|
$10.89 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $25,061 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,457 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2426: Use waste heat from flue gases to heat space conditioning air | $7,713 | $2,370 |
$(-49.0)
(-1,758)
kWh
|
$(-68.0)
-
kW-mo/yr
|
$7,830
-
MMBtu
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,073 | $1,800 |
$1,427
51,098
kWh
|
$1,646
-
kW-mo/yr
|
- | - | |
03 | 2.2511: Insulate bare equipment | $2,679 | $543 | - | - |
$2,679
-
MMBtu
|
- | |
04 | 2.2442: Preheat combustion air with waste heat | $2,635 | $2,695 | - | - |
$2,635
-
MMBtu
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $2,388 | $625 |
$1,107
39,669
kWh
|
$1,281
-
kW-mo/yr
|
- | - | |
06 | 2.4239: Eliminate or reduce compressed air usage | $1,532 | $600 |
$713
25,479
kWh
|
$819
-
kW-mo/yr
|
- | - | |
07 | 2.7144: Install spectral reflectors / delamp | $1,368 | $2,700 |
$549
19,762
kWh
|
$819
-
kW-mo/yr
|
- | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,253 | $1,270 |
$631
22,387
kWh
|
$722
-
kW-mo/yr
|
- | $(-100.0) | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $850 | - |
$396
14,151
kWh
|
$454
-
kW-mo/yr
|
- | - | |
10 | 2.2628: Utilize a less expensive cooling method | $571 | $525 |
$287
10,255
kWh
|
$284
-
kW-mo/yr
|
- | - | |
11 | 2.4151: Develop a repair/replace policy | $501 | $213 |
$372
13,185
kWh
|
$429
-
kW-mo/yr
|
- | $(-300.0) | |
12 | 2.2625: Chill water to the highest temperature possible | $498 | $25 |
$230
8,262
kWh
|
$268
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $25,061 | $13,366 |
$5,663
202,490
kWh
|
$6,654
-
kW-mo/yr
|
$13,144
-
MMBtu
|
$(-400.0) | ||
TOTAL IMPLEMENTED | $18,457 | $6,821 |
$3,884
138,732
kWh
|
$4,464
-
kW-mo/yr
|
$10,509
-
MMBtu
|
$(-400.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs