Assessment Year | 2006 |
---|---|
Principal Product | Porcelain Insulators |
NAICS | 327110: Pottery, Ceramics, and Plumbing Fixture Manufacturing |
SIC | 3264: Porcelain Electrical Supplies |
Sales Range | $10 M to 50M |
# of Employees | 116 |
Plant Area |
350,000
ft2
|
Annual Production | 1,200
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $213,875 | 3,657,253 |
kWh
|
$0.058 |
Electricity Demand | $102,063 | 10,598 |
kW-mo/yr
|
$9.63 |
Electricity Fees | $7,563 | - |
|
- |
Natural Gas | $948,148 | 116,418 |
MMBtu
|
$8.14 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $71,583 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $35,527 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $14,635 | - | - | - | - | - | $14,635 | |
02 | 4.821: Pay bills on time to avoid late fees | $12,392 | - | - | - | - | - | $12,392 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,878 | - |
$5,212
89,856
kWh
|
$1,666
-
kW-mo/yr
|
- | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,547 | - |
$3,189
54,990
kWh
|
$1,358
-
kW-mo/yr
|
- | - | - | |
05 | 2.4314: Use synthetic lubricant | $3,930 | - |
$2,755
47,502
kWh
|
$1,175
-
kW-mo/yr
|
- | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,224 | - |
$2,502
43,130
kWh
|
$722
-
kW-mo/yr
|
- | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,893 | $630 |
$3,113
53,680
kWh
|
$780
-
kW-mo/yr
|
- | - | - | |
08 | 2.1232: Keep boiler tubes clean | $5,210 | $1,534 | - | - |
$5,210
-
MMBtu
|
- | - | |
09 | 2.4221: Install compressor air intakes in coolest locations | $1,794 | $563 |
$1,419
24,460
kWh
|
$375
-
kW-mo/yr
|
- | - | - | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $238 | $313 |
$85
1,454
kWh
|
$19
-
kW-mo/yr
|
- | $64 | $70 | |
11 | 2.7135: Install occupancy sensors | $145 | $222 |
$145
2,496
kWh
|
- | - | - | - | |
12 | 2.2414: Use waste heat from hot flue gases to preheat | $13,544 | $26,000 | - | - |
$13,544
-
MMBtu
|
- | - | |
13 | 2.6211: Conserve energy by efficient use of vending machines | $372 | $845 |
$305
5,256
kWh
|
$67
-
kW-mo/yr
|
- | - | - | |
14 | 2.2511: Insulate bare equipment | $781 | $2,198 | - | - |
$781
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $71,583 | $32,305 |
$18,725
322,824
kWh
|
$6,162
-
kW-mo/yr
|
$19,535
-
MMBtu
|
$64 | $27,097 | ||
TOTAL IMPLEMENTED | $35,527 | $2,164 |
$13,582
234,168
kWh
|
$4,343
-
kW-mo/yr
|
$5,210
-
MMBtu
|
- | $12,392 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs