ITAC Assessment: WV0329
ITAC logo
ITAC Assessment: WV0329
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Iron and Steel Castings
NAICS 333613: Mechanical Power Transmission Equipment Manufacturing
SIC 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 332
Plant Area 440,000
ft2
Annual Production 41,250,000
lb
Production Hrs. Annual 7,488
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $542,669 13,369,600
kWh
Electricity Demand $170,952 32,255
kW-mo/yr
Electricity Fees $(-47,385.0) -
Natural Gas $565,064 68,657
MMBtu
Fuel Oil #2 $17,820 1,512
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $115,637 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $78,660

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #2 Savings Personnel Changes Savings Primary Raw Material Savings
01 2.7231: Use radiant heater for spot heating $35,587 $11,800 - - $35,587
-
MMBtu
- - -
02 2.2514: Cover open tanks $19,992 $60,000 - - $19,992
-
MMBtu
- - -
03 2.2437: Recover waste heat from equipment $16,985 $1,088 - - $16,985
-
MMBtu
- - -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $12,841 $10,360 $9,698
239,088
kWh
$3,143
-
kW-mo/yr
- - - -
05 2.7232: Replace existing hvac unit with high efficiency model $9,423 $8,360 - - $(-8,397.0)
-
MMBtu
$17,820
-
MMBtu
- -
06 2.4151: Develop a repair/replace policy $6,007 $729 $5,119
126,283
kWh
$1,320
-
kW-mo/yr
- - $(-432.0) -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $5,535 $8,398 $4,364
107,439
kWh
$1,171
-
kW-mo/yr
- - - -
08 2.7232: Replace existing hvac unit with high efficiency model $4,468 $11,504 $2,973
73,250
kWh
$1,495
-
kW-mo/yr
- - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $3,268 - $2,702
66,554
kWh
$566
-
kW-mo/yr
- - - -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $799 $299 $773
18,993
kWh
$164
-
kW-mo/yr
- - $(-108.0) $(-30.0)
11 2.4221: Install compressor air intakes in coolest locations $732 $294 $605
14,918
kWh
$127
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $115,637 $112,832 $26,234
646,525
kWh
$7,986
-
kW-mo/yr
$64,167
-
MMBtu
$17,820
-
MMBtu
$(-540.0) $(-30.0)
TOTAL IMPLEMENTED $78,660 $51,744 $26,234
646,525
kWh
$7,986
-
kW-mo/yr
$27,190
-
MMBtu
$17,820
-
MMBtu
$(-540.0) $(-30.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #2 Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs