ITAC Assessment: WV0325
ITAC logo
ITAC Assessment: WV0325
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Rubber Seals for Automotive Vehicles
NAICS 339991: Gasket, Packing, and Sealing Device Manufacturing
SIC 3053: Gaskets, Packing, and Sealing Devices
Sales Range $5
M
to 10
M
# of Employees 100
Plant Area 155,000
ft2
Annual Production 2,204,623
lb
Production Hrs. Annual 6,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $260,035 4,031,100
kWh
Electricity Fees $11,783 -
Natural Gas $54,816 6,008
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $58,033 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $26,269

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7231: Use radiant heater for spot heating $16,088 $12,504 - - $16,088
-
MMBtu
- -
02 2.3212: Optimize plant power factor $10,956 $11,550 - $10,956 - - -
03 2.7111: Reduce illumination to minimum necessary levels $7,144 $662 $7,144
110,880
kWh
- - - -
04 2.7224: Reduce space conditioning during non-working hours $7,050 $653 - - $7,050
-
MMBtu
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $5,009 - $5,009
77,880
kWh
- - - -
06 2.2437: Recover waste heat from equipment $3,529 $408 - - $3,529
-
MMBtu
- -
07 2.4151: Develop a repair/replace policy $2,990 $257 $3,242
50,279
kWh
- - $(-252.0) -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,637 $420 $2,003
31,063
kWh
- - $(-126.0) $(-240.0)
09 2.7135: Install occupancy sensors $851 $426 $851
13,176
kWh
- - - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $832 $2,612 $832
12,882
kWh
- - - -
11 2.2628: Utilize a less expensive cooling method $775 $521 $775
12,055
kWh
- - - -
12 2.4231: Reduce the pressure of compressed air to the minimum required $756 $260 $756
11,850
kWh
- - - -
13 2.4221: Install compressor air intakes in coolest locations $416 $276 $416
6,362
kWh
- - - -
TOTAL RECOMMENDED $58,033 $30,549 $21,028
326,427
kWh
$10,956 $26,667
-
MMBtu
$(-378.0) $(-240.0)
TOTAL IMPLEMENTED $26,269 $5,290 $19,837
308,010
kWh
- $7,050
-
MMBtu
$(-378.0) $(-240.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs