ITAC Assessment: UM0321
ITAC logo
ITAC Assessment: UM0321
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Carbonated and Non-Carbonated Soft Drinks
NAICS 312111: Soft Drink Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $100
M
to 500
M
# of Employees 145
Plant Area 363,897
ft2
Annual Production 28,000,000
pieces
Production Hrs. Annual 7,488
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $423,638 9,227,524
kWh
Electricity Demand $301,148 18,849
kW-mo/yr
Electricity Fees $43,017 -
Natural Gas $487,232 50,071
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $71,255 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,196

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Consumption Savings
01 2.7234: Use heat pump for space conditioning $33,455 $21,730 $(-3,089.0)
(-37,211)
kWh
$(-556.0)
-
kW-mo/yr
$37,100
-
MMBtu
-
02 2.7491: Insulate glazing, walls, ceilings, and roofs $11,520 $21,700 - - $11,520
-
MMBtu
-
03 2.7224: Reduce space conditioning during non-working hours $9,993 $1,000 - - $9,993
-
MMBtu
-
04 2.1233: Analyze flue gas for proper air/fuel ratio $7,307 $1,000 - - $7,307
-
MMBtu
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $4,338 - $2,785
60,653
kWh
$1,553
-
kW-mo/yr
- -
06 3.4113: Treat and reuse rinse waters $3,084 $8,021 - - - $3,084
-
Tgal
07 2.7135: Install occupancy sensors $1,558 $5,130 $1,558
33,940
kWh
- - -
TOTAL RECOMMENDED $71,255 $58,581 $1,254
57,382
kWh
$997
-
kW-mo/yr
$65,920
-
MMBtu
$3,084
-
Tgal
TOTAL IMPLEMENTED $23,196 $7,130 $4,343
94,593
kWh
$1,553
-
kW-mo/yr
$17,300
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs