Assessment Year | 2005 |
---|---|
Principal Product | Machine Tool Products |
NAICS | 331529: Other Nonferrous Metal Foundries (except Die-Casting) |
SIC | 3366: Copper Foundries |
Sales Range | $10 M to 50M |
# of Employees | 165 |
Plant Area |
104,000
ft2
|
Annual Production | 10,400,000
pieces
|
Production Hrs. Annual | 6,656
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $144,112 | 1,807,200 |
kWh
|
$0.080 |
Electricity Demand | $33,233 | 4,966 |
kW-mo/yr
|
$6.69 |
Electricity Fees | $593 | - |
|
- |
Natural Gas | $19,012 | 1,735 |
MMBtu
|
$10.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $46,505 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $34,033 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,626 | $30,000 |
$13,572
170,287
kWh
|
$2,054
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,978 | $5,805 |
$4,322
54,151
kWh
|
$656
-
kW-mo/yr
|
- | - | - | - | |
03 | 3.6124: Burn waste oil for heat | $4,770 | $4,000 | - | - |
$3,650
-
MMBtu
|
$1,120
-
gal
|
- | - | |
04 | 2.7135: Install occupancy sensors | $4,359 | $4,750 |
$3,784
47,517
kWh
|
$575
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $4,094 | $2,700 |
$3,177
39,848
kWh
|
$917
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,232 | - |
$2,804
35,144
kWh
|
$428
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4227: Use compressor air filters | $2,183 | $800 |
$1,896
23,780
kWh
|
$287
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.2437: Recover waste heat from equipment | $1,732 | $1,645 | - | - |
$1,732
-
MMBtu
|
- | - | - | |
09 | 2.4151: Develop a repair/replace policy | $1,621 | $213 |
$1,929
24,026
kWh
|
$292
-
kW-mo/yr
|
- | - | $(-600.0) | - | |
10 | 2.2442: Preheat combustion air with waste heat | $975 | $955 | - | - |
$975
-
MMBtu
|
- | - | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $728 | $667 |
$654
8,322
kWh
|
$74
-
kW-mo/yr
|
- | - | - | - | |
12 | 2.4221: Install compressor air intakes in coolest locations | $487 | $400 |
$420
5,290
kWh
|
$67
-
kW-mo/yr
|
- | - | - | - | |
13 | 2.2628: Utilize a less expensive cooling method | $474 | $488 |
$327
4,242
kWh
|
$147
-
kW-mo/yr
|
- | - | - | - | |
14 | 2.4231: Reduce the pressure of compressed air to the minimum required | $457 | $430 |
$397
4,982
kWh
|
$60
-
kW-mo/yr
|
- | - | - | - | |
15 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $438 | $80 |
$1,004
12,562
kWh
|
$154
-
kW-mo/yr
|
- | - | $(-600.0) | $(-120.0) | |
16 | 2.1135: Repair furnaces and oven doors so that they seal efficiently | $351 | $26 |
$304
3,809
kWh
|
$47
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $46,505 | $52,959 |
$34,590
433,960
kWh
|
$5,758
-
kW-mo/yr
|
$6,357
-
MMBtu
|
$1,120
-
gal
|
$(-1,200.0) | $(-120.0) | ||
TOTAL IMPLEMENTED | $34,033 | $46,290 |
$28,839
361,695
kWh
|
$4,782
-
kW-mo/yr
|
$1,732
-
MMBtu
|
- | $(-1,200.0) | $(-120.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs