ITAC Assessment: WV0318
ITAC logo
ITAC Assessment: WV0318
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Aluminum Extrusions
NAICS 331318: Other Aluminum Rolling, Drawing, and Extruding
SIC 3354: Aluminum Extruded Products
Sales Range $10
M
to 50
M
# of Employees 350
Plant Area 250,000
ft2
Annual Production 8,000,000
lb
Production Hrs. Annual 6,864
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $862,751 10,810,288
kWh
Electricity Demand $478,777 28,719
kW-mo/yr
Electricity Fees $16,083 -
Natural Gas $558,049 73,019
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $114,160 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $104,604

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7243: Improve air circulation with destratification fans / other methods $39,332 $8,388 $(-695.0)
(-19,551)
kWh
$(-895.0)
-
kW-mo/yr
$40,922
-
MMBtu
- -
02 2.2437: Recover waste heat from equipment $21,012 $3,064 $541
15,134
kWh
$217
-
kW-mo/yr
$20,254
-
MMBtu
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $13,845 $6,470 $7,770
218,695
kWh
$6,075
-
kW-mo/yr
- - -
04 2.4239: Eliminate or reduce compressed air usage $12,757 $620 $7,006
197,180
kWh
$5,751
-
kW-mo/yr
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,670 $587 $5,361
150,749
kWh
$4,401
-
kW-mo/yr
- $(-572.0) $(-520.0)
06 2.2514: Cover open tanks $5,974 $12,120 - - $5,974
-
MMBtu
- -
07 2.4151: Develop a repair/replace policy $4,198 $330 $2,592
72,957
kWh
$2,134
-
kW-mo/yr
- $(-528.0) -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $3,582 $11,537 $1,724
48,526
kWh
$1,858
-
kW-mo/yr
- - -
09 2.4221: Install compressor air intakes in coolest locations $3,258 $360 $1,791
50,170
kWh
$1,467
-
kW-mo/yr
- - -
10 2.7232: Replace existing hvac unit with high efficiency model $1,532 $5,220 $665
12,306
kWh
$867
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $114,160 $48,696 $26,755
746,166
kWh
$21,875
-
kW-mo/yr
$67,150
-
MMBtu
$(-1,100.0) $(-520.0)
TOTAL IMPLEMENTED $104,604 $25,039 $25,031
697,640
kWh
$20,017
-
kW-mo/yr
$61,176
-
MMBtu
$(-1,100.0) $(-520.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs