ITAC Assessment: WV0317
ITAC logo
ITAC Assessment: WV0317
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Hose and Tubing
NAICS 331210: Iron and Steel Pipe and Tube Manufacturing from Purchased Steel
SIC 3082: Unsupported Plastics Profile Shapes
Sales Range $50
M
to 100
M
# of Employees 250
Plant Area 160,000
ft2
Annual Production 180,000
thousand feet
Production Hrs. Annual 8,760
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $164,861 9,297,199
kWh
Electricity Demand $263,729 15,625
kW-mo/yr
Electricity Fees $60,117 -
Natural Gas $95,444 12,083
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $96,900 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $29,932

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $28,323 - - $39,273
-
kW-mo/yr
- $(-10,950.0)
02 2.7231: Use radiant heater for spot heating $23,795 $50,000 - - $23,795
-
MMBtu
-
03 2.2628: Utilize a less expensive cooling method $13,415 $5,677 $4,609
190,450
kWh
$8,806
-
kW-mo/yr
- -
04 2.4239: Eliminate or reduce compressed air usage $6,217 $490 $3,180
131,400
kWh
$3,037
-
kW-mo/yr
- -
05 2.6212: Turn off equipment during breaks, reduce operating time $6,041 $60 $6,041
249,660
kWh
- - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,531 $680 $2,687
111,094
kWh
$2,564
-
kW-mo/yr
- $(-720.0)
07 2.4151: Develop a repair/replace policy $4,392 $855 $2,983
123,353
kWh
$2,849
-
kW-mo/yr
- $(-1,440.0)
08 2.2511: Insulate bare equipment $4,285 $128 $2,193
90,537
kWh
$2,092
-
kW-mo/yr
- -
09 2.2414: Use waste heat from hot flue gases to preheat $2,086 $2,295 - - $2,086
-
MMBtu
-
10 2.4151: Develop a repair/replace policy $1,435 $2,075 $734
30,296
kWh
$701
-
kW-mo/yr
- -
11 2.7135: Install occupancy sensors $1,219 $2,680 $1,219
50,458
kWh
- - -
12 2.4221: Install compressor air intakes in coolest locations $761 $205 $390
16,092
kWh
$371
-
kW-mo/yr
- -
13 2.7111: Reduce illumination to minimum necessary levels $400 $240 $206
8,410
kWh
$194
-
kW-mo/yr
- -
TOTAL RECOMMENDED $96,900 $65,385 $24,242
1,001,750
kWh
$59,887
-
kW-mo/yr
$25,881
-
MMBtu
$(-13,110.0)
TOTAL IMPLEMENTED $29,932 $7,633 $18,899
781,004
kWh
$11,107
-
kW-mo/yr
$2,086
-
MMBtu
$(-2,160.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs