Assessment Year | 2005 |
---|---|
Principal Product | Specialty Chemicals |
NAICS | 424690: Other Chemical and Allied Products Merchant Wholesalers |
SIC | 5169: Chemicals and Allied Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 116 |
Plant Area |
300,000
ft2
|
Annual Production | 0
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $256,710 | 12,536,120 |
kWh
|
$0.020 |
Electricity Demand | $192,164 | 22,937 |
kW-mo/yr
|
$8.38 |
Electricity Fees | $12,519 | - |
|
- |
Natural Gas | $987,800 | 144,403 |
MMBtu
|
$6.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $233,246 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $137,430 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2113: Repair or replace steam traps | $94,235 | $1,000 | - | - |
$102,155
-
MMBtu
|
- | $(-7,920.0) | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $28,522 | $10,250 | - | - |
$28,522
-
MMBtu
|
- | - | |
03 | 2.1212: Operate boilers on high fire setting | $27,626 | $5,110 | - | - |
$27,626
-
MMBtu
|
- | - | |
04 | 2.2625: Chill water to the highest temperature possible | $21,789 | $110 |
$14,197
661,264
kWh
|
$7,592
-
kW-mo/yr
|
- | - | - | |
05 | 2.2135: Repair and eliminate steam leaks | $15,992 | $3,200 | - | - |
$15,992
-
MMBtu
|
- | - | |
06 | 3.4151: Minimize water usage | $14,331 | $13,600 | - | - |
$12,333
-
MMBtu
|
$1,998
-
Tgal
|
- | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,376 | $900 |
$6,108
284,467
kWh
|
$3,268
-
kW-mo/yr
|
- | - | - | |
08 | 2.2511: Insulate bare equipment | $4,952 | $1,322 | - | - |
$4,952
-
MMBtu
|
- | - | |
09 | 2.4151: Develop a repair/replace policy | $3,756 | $1,320 |
$3,307
154,118
kWh
|
$1,769
-
kW-mo/yr
|
- | - | $(-1,320.0) | |
10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,479 | $110 |
$2,264
105,845
kWh
|
$1,215
-
kW-mo/yr
|
- | - | - | |
11 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,420 | $1,000 | - | - |
$3,420
-
MMBtu
|
- | - | |
12 | 2.4314: Use synthetic lubricant | $2,220 | $620 |
$1,447
67,390
kWh
|
$773
-
kW-mo/yr
|
- | - | - | |
13 | 2.2628: Utilize a less expensive cooling method | $2,101 | - |
$2,541
118,372
kWh
|
$1,358
-
kW-mo/yr
|
- | - | $(-1,798.0) | |
14 | 2.4221: Install compressor air intakes in coolest locations | $1,447 | $1,050 |
$944
44,101
kWh
|
$503
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $233,246 | $39,592 |
$30,808
1,435,557
kWh
|
$16,478
-
kW-mo/yr
|
$195,000
-
MMBtu
|
$1,998
-
Tgal
|
$(-11,038.0) | ||
TOTAL IMPLEMENTED | $137,430 | $9,472 |
$13,126
611,820
kWh
|
$7,025
-
kW-mo/yr
|
$126,519
-
MMBtu
|
- | $(-9,240.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs