ITAC Assessment: WV0310
ITAC logo
ITAC Assessment: WV0310
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Coupling of Motors and Other Equipment
NAICS 332919: Other Metal Valve and Pipe Fitting Manufacturing
SIC 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 170
Plant Area 120,000
ft2
Annual Production 2,600,000
pieces
Production Hrs. Annual 6,656
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $121,166 3,036,717
kWh
Electricity Demand $65,945 6,434
kW-mo/yr
Electricity Fees $8,362 -
Natural Gas $54,104 6,959
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,500 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $14,059 $8,260 $9,810
229,935
kWh
$4,249
-
kW-mo/yr
- - -
02 2.7243: Improve air circulation with destratification fans / other methods $6,573 $8,352 $(-635.0)
(-14,896)
kWh
$(-550.0)
-
kW-mo/yr
- $7,758
-
MMBtu
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $4,268 - $2,976
69,536
kWh
$1,292
-
kW-mo/yr
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,968 $11,900 $2,456
57,574
kWh
$1,512
-
kW-mo/yr
- - -
05 2.3212: Optimize plant power factor $2,190 $820 - - $2,190 - -
06 2.4151: Develop a repair/replace policy $1,229 $304 $1,663
38,969
kWh
$718
-
kW-mo/yr
- - $(-1,152.0)
07 2.4322: Use or replace with energy efficient substitutes $1,763 $336 $1,230
28,829
kWh
$533
-
kW-mo/yr
- - -
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,536 $870 $1,075
25,198
kWh
$461
-
kW-mo/yr
- - -
09 2.4221: Install compressor air intakes in coolest locations $951 $238 $664
15,540
kWh
$287
-
kW-mo/yr
- - -
10 2.4231: Reduce the pressure of compressed air to the minimum required $943 $24 $658
15,423
kWh
$285
-
kW-mo/yr
- - -
11 2.7135: Install occupancy sensors $921 $2,268 $616
14,444
kWh
$305
-
kW-mo/yr
- - -
12 2.7492: Use proper thickness of insulation on building envelope $560 $145 - - - $560
-
MMBtu
-
13 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $539 $132 $376
8,817
kWh
$163
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $39,500 $33,649 $20,889
489,369
kWh
$9,255
-
kW-mo/yr
$2,190 $8,318
-
MMBtu
$(-1,152.0)
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs