Assessment Year | 2004 |
---|---|
Principal Product | Kitchen Cabinet Components |
NAICS | 337110: Wood Kitchen Cabinet and Countertop Manufacturing |
SIC | 2434: Wood Kitchen Cabinets |
Sales Range | $50 M to 100M |
# of Employees | 700 |
Plant Area |
320,000
ft2
|
Annual Production | 7,250,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $559,504 | 17,032,488 |
kWh
|
$0.033 |
Electricity Demand | $263,967 | 40,405 |
kW-mo/yr
|
$6.53 |
Electricity Fees | $(-18,534.0) | - |
|
- |
Wood | $36,592 | 80,914 |
MMBtu
|
$0.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $68,825 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,940 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,432 | - |
$9,068
285,296
kWh
|
$4,364
-
kW-mo/yr
|
- | - | |
02 | 2.4151: Develop a repair/replace policy | $8,151 | $458 |
$6,081
191,329
kWh
|
$2,619
-
kW-mo/yr
|
- | $(-549.0) | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,999 | $3,622 |
$4,962
156,169
kWh
|
$2,037
-
kW-mo/yr
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,262 | $137 |
$2,225
70,038
kWh
|
$1,037
-
kW-mo/yr
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,576 | $8,537 |
$1,434
45,198
kWh
|
$1,142
-
kW-mo/yr
|
- | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $2,414 | $618 |
$1,620
51,008
kWh
|
$794
-
kW-mo/yr
|
- | - | |
07 | 2.4314: Use synthetic lubricant | $1,981 | $560 |
$1,327
41,757
kWh
|
$654
-
kW-mo/yr
|
- | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,770 | $236 |
$1,182
37,300
kWh
|
$588
-
kW-mo/yr
|
- | - | |
09 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $1,586 | $2,606 |
$1,220
38,383
kWh
|
$366
-
kW-mo/yr
|
- | - | |
10 | 2.4322: Use or replace with energy efficient substitutes | $1,061 | $414 |
$754
23,625
kWh
|
$307
-
kW-mo/yr
|
- | - | |
11 | 2.2437: Recover waste heat from equipment | $816 | $515 | - | - |
$816
-
MMBtu
|
- | |
12 | 2.7135: Install occupancy sensors | $606 | $2,422 |
$319
10,057
kWh
|
$287
-
kW-mo/yr
|
- | - | |
13 | 2.2511: Insulate bare equipment | $171 | $303 | - | - |
$171
-
MMBtu
|
- | |
14 | 3.5311: Recover and reuse waste material | $24,000 | $458 | - | - |
$24,000
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $68,825 | $20,886 |
$30,192
950,160
kWh
|
$14,195
-
kW-mo/yr
|
$24,987
-
MMBtu
|
$(-549.0) | ||
TOTAL IMPLEMENTED | $18,940 | $11,641 |
$12,398
390,217
kWh
|
$6,104
-
kW-mo/yr
|
$987
-
MMBtu
|
$(-549.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs