| Assessment Year | 2004 |
|---|---|
| Principal Product | Activated Carbon |
| NAICS | 322230: Stationery Product Manufacturing |
| SIC | 2677: Envelopes |
| Sales Range | $10 M to 50M |
| # of Employees | 120 |
| Plant Area |
12,000
ft2
|
| Annual Production | 10,000
ton
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $239,722 | 6,868,825 |
kWh
|
$0.035 |
| Natural Gas | $521,550 | 61,275 |
MMBtu
|
$8.51 |
| Other Energy | $130,837 | 37,429 |
MMBtu
|
$3.50 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $176,514 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,107 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $121,920 | $33,990 | - |
$121,920
-
MMBtu
|
- | |
| 02 | 2.1221: Replace obsolete burners with more efficient ones | $25,862 | $55,500 | - |
$25,862
-
MMBtu
|
- | |
| 03 | 2.2414: Use waste heat from hot flue gases to preheat | $18,874 | $6,254 | - |
$18,874
-
MMBtu
|
- | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,905 | $1,326 |
$2,905
83,212
kWh
|
- | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,307 | $108 |
$2,307
64,848
kWh
|
- | - | |
| 06 | 2.2135: Repair and eliminate steam leaks | $1,262 | $1,200 | - | - |
$1,262
-
MMBtu
|
|
| 07 | 2.4151: Develop a repair/replace policy | $1,041 | $142 |
$1,041
39,145
kWh
|
- | - | |
| 08 | 2.2113: Repair or replace steam traps | $799 | $1,000 | - | - |
$799
-
MMBtu
|
|
| 09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $793 | $94 |
$793
22,219
kWh
|
- | - | |
| 10 | 2.4221: Install compressor air intakes in coolest locations | $751 | $282 |
$751
21,120
kWh
|
- | - | |
| TOTAL RECOMMENDED | $176,514 | $99,896 |
$7,797
230,544
kWh
|
$166,656
-
MMBtu
|
$2,061
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $9,107 | $3,870 |
$7,046
209,424
kWh
|
- |
$2,061
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs