| Assessment Year | 2004 |
|---|---|
| Principal Product | Electrical and Mechanical Cables |
| NAICS | 335931: Current-Carrying Wiring Device Manufacturing |
| SIC | 3643: Current-Carrying Wiring Devices |
| Sales Range | $10 M to 50M |
| # of Employees | 125 |
| Plant Area |
341,000
ft2
|
| Annual Production | 15,000
ton
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $310,204 | 5,193,719 |
kWh
|
$0.060 |
| Natural Gas | $93,264 | 12,390 |
MMBtu
|
$7.53 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $119,374 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $40,881 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Water Disposal Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2622: Replace existing chiller with high efficiency model | $46,305 | $117,949 |
$46,305
775,278
kWh
|
- | - | |
| 02 | 2.2696: Use excess cold process fluid for industrial cooling needs | $16,901 | $11,831 | - |
$16,901
-
Tgal
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,600 | $4,857 |
$12,600
210,862
kWh
|
- | - | |
| 04 | 2.4151: Develop a repair/replace policy | $9,956 | $2,109 |
$10,968
183,711
kWh
|
- | $(-1,012.0) | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $6,230 | $1,687 |
$6,230
104,318
kWh
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,338 | $19,000 |
$5,338
89,500
kWh
|
- | - | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,340 | $127 |
$4,340
72,664
kWh
|
- | - | |
| 08 | 2.7135: Install occupancy sensors | $3,010 | $5,938 |
$3,010
50,396
kWh
|
- | - | |
| 09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,993 | $250 |
$2,993
49,959
kWh
|
- | - | |
| 10 | 2.4322: Use or replace with energy efficient substitutes | $2,879 | $511 |
$2,879
48,195
kWh
|
- | - | |
| 11 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,432 | $3,500 |
$2,432
40,716
kWh
|
- | - | |
| 12 | 2.7492: Use proper thickness of insulation on building envelope | $2,170 | $103 |
$2,170
36,332
kWh
|
- | - | |
| 13 | 2.4221: Install compressor air intakes in coolest locations | $1,628 | $1,119 |
$1,628
27,249
kWh
|
- | - | |
| 14 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,227 | $1,631 |
$1,227
20,539
kWh
|
- | - | |
| 15 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,365 | - |
$1,365
23,064
kWh
|
- | - | |
| TOTAL RECOMMENDED | $119,374 | $170,612 |
$103,485
1,732,783
kWh
|
$16,901
-
Tgal
|
$(-1,012.0) | ||
| TOTAL IMPLEMENTED | $40,881 | $10,764 |
$41,893
701,449
kWh
|
- | $(-1,012.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Water Disposal Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs