ITAC Assessment: WV0288
ITAC logo
ITAC Assessment: WV0288
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Copper and Aluminum Tubing
NAICS 331420: Copper Rolling, Drawing, Extruding, and Alloying
SIC 3351: Rolling, Drawing, and Extruding Of Copper
Sales Range $10
M
to 50
M
# of Employees 95
Plant Area 140,000
ft2
Annual Production 4,500,000
lb
Production Hrs. Annual 6,864
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $180,539 2,475,900
kWh
Electricity Demand $43,700 6,559
kW-mo/yr
Electricity Fees $2,953 -
Natural Gas $187,020 20,215
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $71,037 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,667

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.2414: Use waste heat from hot flue gases to preheat $12,469 $2,195 - - $12,469
-
MMBtu
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $9,141 $360 $7,902
106,661
kWh
$1,239
-
kW-mo/yr
- -
03 2.4322: Use or replace with energy efficient substitutes $9,120 $700 $7,881
106,307
kWh
$1,239
-
kW-mo/yr
- -
04 2.7111: Reduce illumination to minimum necessary levels $8,061 $250 $6,969
94,003
kWh
$1,092
-
kW-mo/yr
- -
05 2.2426: Use waste heat from flue gases to heat space conditioning air $6,212 $1,200 $(-282.0)
(-3,809)
kWh
- $6,494
-
MMBtu
-
06 2.1221: Replace obsolete burners with more efficient ones $5,772 $27,600 - - $5,772
-
MMBtu
-
07 2.4151: Develop a repair/replace policy $4,573 $1,000 $4,980
67,976
kWh
$793
-
kW-mo/yr
- $(-1,200.0)
08 2.7142: Utilize higher efficiency lamps and/or ballasts $4,040 $3,210 $3,343
45,045
kWh
$697
-
kW-mo/yr
- -
09 2.4231: Reduce the pressure of compressed air to the minimum required $3,932 $50 $2,654
35,786
kWh
$1,278
-
kW-mo/yr
- -
10 2.4226: Use / purchase optimum sized compressor $3,739 $575 $2,540
34,281
kWh
$1,199
-
kW-mo/yr
- -
11 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,876 $3,500 $1,824
24,612
kWh
$1,052
-
kW-mo/yr
- -
12 2.4111: Utilize energy-efficient belts and other improved mechanisms $804 $1,100 $695
9,376
kWh
$109
-
kW-mo/yr
- -
13 2.2625: Chill water to the highest temperature possible $203 $25 $174
2,471
kWh
$29
-
kW-mo/yr
- -
14 2.4221: Install compressor air intakes in coolest locations $95 $200 $65
846
kWh
$30
-
kW-mo/yr
- -
TOTAL RECOMMENDED $71,037 $41,965 $38,745
523,555
kWh
$8,757
-
kW-mo/yr
$24,735
-
MMBtu
$(-1,200.0)
TOTAL IMPLEMENTED $33,667 $31,010 $18,033
244,212
kWh
$4,568
-
kW-mo/yr
$12,266
-
MMBtu
$(-1,200.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs