Assessment Year | 1998 |
---|---|
Principal Product | innerspring & boxspring mattresses |
NAICS |
n/a
|
SIC | 2515: Mattresses, Foundations, and Convertible Beds |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
71,000
ft2
|
Annual Production | 625,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $82,808 | 3,222,157 |
kWh
|
$0.026 |
Electricity Demand | $55,863 | 12,705 |
kW-mo/yr
|
$4.40 |
Electricity Fees | $4,404 | - |
|
- |
Natural Gas | $58,395 | 17,040 |
MMBtu
|
$3.43 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,172,230 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,158,130 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $6,210 | $15,400 | - |
$6,210
-
kW-mo/yr
|
- | - | - | - | - | - | |
02 | 2.2437: Recover waste heat from equipment | $6,170 | $8,790 | - | - |
$6,170
-
MMBtu
|
- | - | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,710 | $240 |
$1,990
67,409
kWh
|
$720
-
kW-mo/yr
|
- | - | - | - | - | - | |
04 | 3.5313: Increase amount of waste recovered for resale | $10,420 | $600 | - | - | - | - |
$10,420
-
lb
|
- | - | - | |
05 | 3.8132: Use less toxic and volatile solvent substitutes | $1,380 | $3,000 |
$(-170.0)
(-5,862)
kWh
|
$(-60.0)
-
kW-mo/yr
|
- |
$2,890
-
gal
|
- | - | - | $(-1,280.0) | |
06 | 3.6192: Use a less expensive method of waste removal | $340 | - | - | - | - | - | - |
$340
-
lb
|
- | - | |
07 | 4.322: Eliminate old stock and modify inventory control | $1,145,000 | $210,480 | - | - | - | - | - | - | $1,145,000 | - | |
TOTAL RECOMMENDED | $1,172,230 | $238,510 |
$1,820
61,547
kWh
|
$6,870
-
kW-mo/yr
|
$6,170
-
MMBtu
|
$2,890
-
gal
|
$10,420
-
lb
|
$340
-
lb
|
$1,145,000 | $(-1,280.0) | ||
TOTAL IMPLEMENTED | $1,158,130 | $211,320 |
$1,990
67,409
kWh
|
$720
-
kW-mo/yr
|
- | - |
$10,420
-
lb
|
- | $1,145,000 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs