Assessment Year | 2004 |
---|---|
Principal Product | Custom Rubber Products |
NAICS | 326299: All Other Rubber Product Manufacturing |
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 43 |
Plant Area |
25,000
ft2
|
Annual Production | 750,000
lb
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $75,035 | 1,408,080 |
kWh
|
$0.053 |
Electricity Demand | $27,403 | 5,048 |
kW-mo/yr
|
$5.43 |
Natural Gas | $8,163 | 925 |
MMBtu
|
$8.82 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $24,424 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,103 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $12,938 | $1 |
$10,786
202,463
kWh
|
$2,152
-
kW-mo/yr
|
- | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $4,455 | - | - |
$4,455
-
kW-mo/yr
|
- | |
03 | 2.4151: Develop a repair/replace policy | $1,782 | $450 |
$1,937
36,332
kWh
|
$385
-
kW-mo/yr
|
$(-540.0) | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,648 | $30 |
$1,374
25,795
kWh
|
$274
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,310 | - |
$1,092
20,465
kWh
|
$218
-
kW-mo/yr
|
- | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,069 | $250 |
$890
16,848
kWh
|
$179
-
kW-mo/yr
|
- | |
07 | 2.4221: Install compressor air intakes in coolest locations | $448 | $240 |
$375
6,838
kWh
|
$73
-
kW-mo/yr
|
- | |
08 | 2.4322: Use or replace with energy efficient substitutes | $418 | $200 |
$349
6,552
kWh
|
$69
-
kW-mo/yr
|
- | |
09 | 2.4314: Use synthetic lubricant | $356 | $215 |
$297
5,567
kWh
|
$59
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $24,424 | $1,386 |
$17,100
320,860
kWh
|
$7,864
-
kW-mo/yr
|
$(-540.0) | ||
TOTAL IMPLEMENTED | $19,103 | $946 |
$16,376
307,470
kWh
|
$3,267
-
kW-mo/yr
|
$(-540.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs