ITAC Assessment: WV0282
ITAC logo
ITAC Assessment: WV0282
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Industrial Fabrication
NAICS 331221: Rolled Steel Shape Manufacturing
SIC 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills
Sales Range $10
M
to 50
M
# of Employees 87
Plant Area 130,000
ft2
Annual Production 1,825
ton
Production Hrs. Annual 4,680
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $138,475 2,988,153
kWh
Natural Gas $124,115 18,401
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $112,375 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $37,148

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings
01 2.7232: Replace existing hvac unit with high efficiency model $33,174 $63,040 - $33,174
-
MMBtu
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $32,062 $4,200 $32,062
691,869
kWh
- - -
03 2.7111: Reduce illumination to minimum necessary levels $17,179 $1,140 $17,179
370,656
kWh
- - -
04 2.4226: Use / purchase optimum sized compressor $3,151 - $3,151
67,915
kWh
- - -
05 3.6124: Burn waste oil for heat $6,148 $3,760 - $1,348
-
MMBtu
$4,800
-
gal
-
06 2.4151: Develop a repair/replace policy $3,646 $1,140 $4,558
98,448
kWh
- - $(-912.0)
07 2.7142: Utilize higher efficiency lamps and/or ballasts $2,390 $4,448 $2,390
51,552
kWh
- - -
08 2.4239: Eliminate or reduce compressed air usage $1,521 $490 $1,521
32,760
kWh
- - -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,387 $250 $1,387
29,915
kWh
- - -
10 2.4111: Utilize energy-efficient belts and other improved mechanisms $923 $715 $923
19,924
kWh
- - -
11 2.2614: Use cooling tower or economizer to replace chiller cooling $788 $614 $788
16,994
kWh
- - -
12 2.4231: Reduce the pressure of compressed air to the minimum required $2,784 $76 $2,784
60,052
kWh
- - -
13 2.4221: Install compressor air intakes in coolest locations $1,534 $250 $1,534
33,101
kWh
- - -
14 2.2522: Isolate hot or cold equipment $5,688 $690 - $5,688
-
MMBtu
- -
TOTAL RECOMMENDED $112,375 $80,813 $68,277
1,473,186
kWh
$40,210
-
MMBtu
$4,800
-
gal
$(-912.0)
TOTAL IMPLEMENTED $37,148 $8,459 $32,372
698,462
kWh
$5,688
-
MMBtu
- $(-912.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs