Assessment Year | 2003 |
---|---|
Principal Product | Paints and Allied Products |
NAICS | 325510: Paint and Coating Manufacturing |
SIC | 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
300,000
ft2
|
Annual Production | 1,000
Tgal
|
Production Hrs. Annual | 6,268
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $254,927 | 3,713,559 |
kWh
|
$0.069 |
Natural Gas | $315,620 | 68,987 |
MMBtu
|
$4.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $138,885 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $97,757 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2423: Install waste heat boiler to produce steam | $41,760 | $60,000 | - |
$41,760
-
MMBtu
|
|
02 | 2.7261: Install timers and/or thermostats | $33,509 | $580 | - |
$33,509
-
MMBtu
|
|
03 | 2.1213: Direct warmest air to combustion intake | $30,964 | $9,195 | - |
$30,964
-
MMBtu
|
|
04 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $8,969 | $500 |
$8,969
130,678
kWh
|
- | |
05 | 2.2515: Use optimum thickness insulation | $8,395 | $2,640 | - |
$8,395
-
MMBtu
|
|
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,737 | $16,926 |
$6,737
98,192
kWh
|
- | |
07 | 2.2113: Repair or replace steam traps | $2,328 | $480 | - |
$2,328
-
MMBtu
|
|
08 | 2.7135: Install occupancy sensors | $2,514 | $2,200 |
$2,514
36,550
kWh
|
- | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,770 | $80 |
$1,770
25,702
kWh
|
- | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,195 | - |
$1,195
17,402
kWh
|
- | |
11 | 2.4221: Install compressor air intakes in coolest locations | $744 | $320 |
$744
10,885
kWh
|
- | |
TOTAL RECOMMENDED | $138,885 | $92,921 |
$21,929
319,409
kWh
|
$116,956
-
MMBtu
|
||
TOTAL IMPLEMENTED | $97,757 | $83,226 |
$11,765
171,329
kWh
|
$85,992
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs