| Assessment Year | 2003 |
|---|---|
| Principal Product | Thermal label ribbons&Jack hammer parts |
| NAICS | 339940: Office Supplies (except Paper) Manufacturing |
| SIC | 3955: Carbon Paper and Inked Ribbons |
| Sales Range | $10 M to 50M |
| # of Employees | 220 |
| Plant Area |
300,000
ft2
|
| Annual Production | 1,605,924
pieces
|
| Production Hrs. Annual | 3,366
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $203,633 | 3,957,055 |
kWh
|
$0.051 |
| Electricity Demand | $75,029 | 11,275 |
kW-mo/yr
|
$6.65 |
| Natural Gas | $125,303 | 17,304 |
MMBtu
|
$7.24 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $86,536 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $77,510 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,435 | $108 |
$4,328
59,069
kWh
|
$1,107
-
kW-mo/yr
|
- | - | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $3,489 | $630 |
$2,783
37,972
kWh
|
$706
-
kW-mo/yr
|
- | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,612 | $250 |
$2,068
28,228
kWh
|
$544
-
kW-mo/yr
|
- | - | |
| 04 | 2.4312: Improve lubrication practices | $1,165 | $810 |
$1,009
13,846
kWh
|
$156
-
kW-mo/yr
|
- | - | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $7,261 | $720 |
$5,552
75,770
kWh
|
$1,709
-
kW-mo/yr
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $27,769 | $20,880 |
$21,227
290,396
kWh
|
$6,542
-
kW-mo/yr
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,262 | - |
$966
13,143
kWh
|
$296
-
kW-mo/yr
|
- | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,404 | $6,834 |
$1,074
14,662
kWh
|
$330
-
kW-mo/yr
|
- | - | |
| 09 | 2.7135: Install occupancy sensors | $927 | $600 |
$709
9,669
kWh
|
$218
-
kW-mo/yr
|
- | - | |
| 10 | 2.2511: Insulate bare equipment | $24,688 | $2,019 | - | - |
$24,688
-
MMBtu
|
- | |
| 11 | 2.2414: Use waste heat from hot flue gases to preheat | $2,827 | $1,855 | - | - |
$2,827
-
MMBtu
|
- | |
| 12 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,545 | - |
$1,181
16,115
kWh
|
$364
-
kW-mo/yr
|
- | - | |
| 13 | 2.4151: Develop a repair/replace policy | $6,152 | $450 |
$5,186
70,906
kWh
|
$1,398
-
kW-mo/yr
|
- | $(-432.0) | |
| TOTAL RECOMMENDED | $86,536 | $35,156 |
$46,083
629,776
kWh
|
$13,370
-
kW-mo/yr
|
$27,515
-
MMBtu
|
$(-432.0) | ||
| TOTAL IMPLEMENTED | $77,510 | $31,861 |
$41,110
561,843
kWh
|
$12,144
-
kW-mo/yr
|
$24,688
-
MMBtu
|
$(-432.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs