Assessment Year | 2003 |
---|---|
Principal Product | Aluminum Can Closure |
NAICS | 332431: Metal Can Manufacturing |
SIC | 3411: Metal Cans |
Sales Range | $100 M to 500M |
# of Employees | 225 |
Plant Area |
216,000
ft2
|
Annual Production | 8,112,000,000
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $293,515 | 14,470,417 |
kWh
|
$0.020 |
Electricity Demand | $140,853 | 24,576 |
kW-mo/yr
|
$5.73 |
Electricity Fees | $171,094 | - |
|
- |
Natural Gas | $33,162 | 4,622 |
MMBtu
|
$7.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $75,271 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $54,612 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $2,420 | $280 | - | - |
$2,420
-
MMBtu
|
- | |
02 | 2.4239: Eliminate or reduce compressed air usage | $23,554 | $3,000 |
$23,004
716,265
kWh
|
$550
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,354 | $150 |
$2,695
83,916
kWh
|
$659
-
kW-mo/yr
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,291 | $30 |
$5,053
157,309
kWh
|
$1,238
-
kW-mo/yr
|
- | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $4,515 | $195 |
$3,628
112,975
kWh
|
$887
-
kW-mo/yr
|
- | - | |
06 | 2.7111: Reduce illumination to minimum necessary levels | $5,119 | $600 |
$3,745
116,614
kWh
|
$1,374
-
kW-mo/yr
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,214 | - |
$4,832
150,455
kWh
|
$1,382
-
kW-mo/yr
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,946 | $3,870 |
$2,269
70,643
kWh
|
$677
-
kW-mo/yr
|
- | - | |
09 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $17,176 | $375 |
$13,900
432,761
kWh
|
$3,816
-
kW-mo/yr
|
- | $(-540.0) | |
10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,291 | $600 |
$1,004
31,267
kWh
|
$287
-
kW-mo/yr
|
- | - | |
11 | 3.6124: Burn waste oil for heat | $2,391 | $3,700 | - | - |
$2,391
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $75,271 | $12,800 |
$60,130
1,872,205
kWh
|
$10,870
-
kW-mo/yr
|
$4,811
-
MMBtu
|
$(-540.0) | ||
TOTAL IMPLEMENTED | $54,612 | $8,025 |
$47,925
1,492,161
kWh
|
$7,227
-
kW-mo/yr
|
- | $(-540.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs