ITAC Assessment: WV0261
ITAC logo
ITAC Assessment: WV0261
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Aluminum Can Closure
NAICS 332431: Metal Can Manufacturing
SIC 3411: Metal Cans
Sales Range $100
M
to 500
M
# of Employees 225
Plant Area 216,000
ft2
Annual Production 8,112,000,000
pieces
Production Hrs. Annual 7,488
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $293,515 14,470,417
kWh
Electricity Demand $140,853 24,576
kW-mo/yr
Electricity Fees $171,094 -
Natural Gas $33,162 4,622
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $75,271 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $54,612

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.7261: Install timers and/or thermostats $2,420 $280 - - $2,420
-
MMBtu
-
02 2.4239: Eliminate or reduce compressed air usage $23,554 $3,000 $23,004
716,265
kWh
$550
-
kW-mo/yr
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,354 $150 $2,695
83,916
kWh
$659
-
kW-mo/yr
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $6,291 $30 $5,053
157,309
kWh
$1,238
-
kW-mo/yr
- -
05 2.4221: Install compressor air intakes in coolest locations $4,515 $195 $3,628
112,975
kWh
$887
-
kW-mo/yr
- -
06 2.7111: Reduce illumination to minimum necessary levels $5,119 $600 $3,745
116,614
kWh
$1,374
-
kW-mo/yr
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $6,214 - $4,832
150,455
kWh
$1,382
-
kW-mo/yr
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $2,946 $3,870 $2,269
70,643
kWh
$677
-
kW-mo/yr
- -
09 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $17,176 $375 $13,900
432,761
kWh
$3,816
-
kW-mo/yr
- $(-540.0)
10 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,291 $600 $1,004
31,267
kWh
$287
-
kW-mo/yr
- -
11 3.6124: Burn waste oil for heat $2,391 $3,700 - - $2,391
-
MMBtu
-
TOTAL RECOMMENDED $75,271 $12,800 $60,130
1,872,205
kWh
$10,870
-
kW-mo/yr
$4,811
-
MMBtu
$(-540.0)
TOTAL IMPLEMENTED $54,612 $8,025 $47,925
1,492,161
kWh
$7,227
-
kW-mo/yr
- $(-540.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs