ITAC Assessment: MO0083
ITAC logo
ITAC Assessment: MO0083
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Molded Polyurethane Soles and Chair
NAICS
n/a
SIC 3021: Rubber and Plastics Footwear
Sales Range $10
M
to 50
M
# of Employees 338
Plant Area 26,900
ft2
Annual Production 16,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $112,073 2,218,933
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,574 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,472

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings LPG Savings Administrative Changes Savings
01 2.2443: Re-use or recycle hot or cold process exhaust air $5,261 $13,500 $467
9,379
kWh
- $4,794
-
MMBtu
-
02 2.6231: Utilize controls to operate equipment only when needed $1,998 $336 $423
8,499
kWh
- $1,575
-
MMBtu
-
03 2.8113: Purchase gas directly from a contract gas supplier $4,773 $75 - - - $4,773
04 2.8113: Purchase gas directly from a contract gas supplier $1,343 $2,703 - - - $1,343
05 2.1233: Analyze flue gas for proper air/fuel ratio $1,699 $2,195 - - $1,699
-
MMBtu
-
06 2.4133: Use most efficient type of electric motors $1,216 $3,873 $1,216
24,033
kWh
- - -
07 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,098 $2,381 $2,234
45,135
kWh
$(-1,136.0)
-
MMBtu
- -
08 2.1311: Replace electrically-operated equipment with fossil fuel equipment $186 $401 $334
6,741
kWh
$(-148.0)
-
MMBtu
- -
TOTAL RECOMMENDED $17,574 $25,464 $4,674
93,787
kWh
$(-1,284.0)
-
MMBtu
$8,068
-
MMBtu
$6,116
TOTAL IMPLEMENTED $6,472 $2,270 - - $1,699
-
MMBtu
$4,773
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings LPG Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs