ITAC Assessment: WV0233
ITAC logo
ITAC Assessment: WV0233
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Plastic totes and Containers
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 209,381
ft2
Annual Production 21,000,000
lb
Production Hrs. Annual 6,600
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $475,395 11,282,400
kWh
Electricity Demand $182,326 23,526
kW-mo/yr
Natural Gas $86,530 7,769
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $101,650 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $52,693

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.2628: Utilize a less expensive cooling method $3,670 $1,375 $2,750
65,266
kWh
$920
-
kW-mo/yr
- - - -
02 2.2437: Recover waste heat from equipment $2,719 $624 - - $2,719
-
MMBtu
- - -
03 2.7232: Replace existing hvac unit with high efficiency model $2,145 $7,000 $1,606
38,090
kWh
$539
-
kW-mo/yr
- - - -
04 2.4221: Install compressor air intakes in coolest locations $988 $272 $741
17,580
kWh
$247
-
kW-mo/yr
- - - -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,409 $3,500 $1,805
42,834
kWh
$604
-
kW-mo/yr
- - - -
06 2.7144: Install spectral reflectors / delamp $616 $720 $309
7,200
kWh
$307
-
kW-mo/yr
- - - -
07 2.7447: Install vinyl strip / high speed / air curtain doors $2,395 $1,590 - - $2,395
-
MMBtu
- - -
08 2.7111: Reduce illumination to minimum necessary levels $11,333 $900 $8,497
201,501
kWh
$2,836
-
kW-mo/yr
- - - -
09 2.7135: Install occupancy sensors $3,539 $750 $2,655
62,995
kWh
$884
-
kW-mo/yr
- - - -
10 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $19,934 $1,800 $14,940
354,530
kWh
$4,994
-
kW-mo/yr
- - - -
11 2.4231: Reduce the pressure of compressed air to the minimum required $934 $50 $700
16,616
kWh
$234
-
kW-mo/yr
- - - -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $8,023 $10,350 $6,014
142,692
kWh
$2,009
-
kW-mo/yr
- - - -
13 3.6124: Burn waste oil for heat $7,659 $2,960 - - $7,659
-
MMBtu
- - -
14 3.6193: Install equipment (eg compactor) to reduce disposal costs $1,875 $740 - - - $1,875
-
gal
- -
15 3.5217: Reuse / recycle/ sell paper products $4,800 $50 - - - - $4,800
-
lb
-
16 4.426: Modify workload $28,611 $5,200 - - - - - $28,611
TOTAL RECOMMENDED $101,650 $37,881 $40,017
949,304
kWh
$13,574
-
kW-mo/yr
$12,773
-
MMBtu
$1,875
-
gal
$4,800
-
lb
$28,611
TOTAL IMPLEMENTED $52,693 $17,107 $33,951
805,385
kWh
$11,547
-
kW-mo/yr
$2,395
-
MMBtu
- $4,800
-
lb
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs