ITAC Assessment: WV0231
ITAC logo
ITAC Assessment: WV0231
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Saw lumber
NAICS
n/a
SIC 2421: Sawmills and Planing Mills, General
Sales Range $5
M
to 10
M
# of Employees 50
Plant Area 85,000
ft2
Annual Production 27,500,000
pieces
Production Hrs. Annual 5,508
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $116,606 5,892,000
kWh
Electricity Demand $110,291 14,436
kW-mo/yr
Wood $41,679 101,608
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,634 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $20,042

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Wood Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,654 $900 $1,786
90,244
kWh
$1,868
-
kW-mo/yr
- - - -
02 2.3212: Optimize plant power factor $1,600 $156 - - $1,600 - - -
03 2.2511: Insulate bare equipment $130 $384 - - - $130
-
MMBtu
- -
04 2.4221: Install compressor air intakes in coolest locations $437 $332 $238
12,013
kWh
$199
-
kW-mo/yr
- - - -
05 2.2414: Use waste heat from hot flue gases to preheat $2,374 $309 - - - $2,374
-
MMBtu
- -
06 2.2437: Recover waste heat from equipment $1,704 $486 $928
46,880
kWh
$776
-
kW-mo/yr
- - - -
07 2.4231: Reduce the pressure of compressed air to the minimum required $745 $12 $406
20,510
kWh
$339
-
kW-mo/yr
- - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $465 $900 $255
12,892
kWh
$210
-
kW-mo/yr
- - - -
09 2.4157: Establish a predictive maintenance program $4,141 $460 $745
20,510
kWh
$3,396
-
kW-mo/yr
- - - -
10 2.6218: Turn off equipment when not in use $6,077 - $605
30,563
kWh
$5,472
-
kW-mo/yr
- - - -
11 3.5217: Reuse / recycle/ sell paper products $3,360 $60 - - - - $3,360
-
lb
-
12 3.6193: Install equipment (eg compactor) to reduce disposal costs $947 $3,000 - - - - $947
-
lb
-
13 4.652: Replace existing equipment with more suitable substitutes $14,000 $6,000 - - - - - $14,000
TOTAL RECOMMENDED $39,634 $12,999 $4,963
233,612
kWh
$12,260
-
kW-mo/yr
$1,600 $2,504
-
MMBtu
$4,307
-
lb
$14,000
TOTAL IMPLEMENTED $20,042 $2,488 $3,797
174,719
kWh
$11,285
-
kW-mo/yr
$1,600 - $3,360
-