ITAC Assessment: WV0225
ITAC logo
ITAC Assessment: WV0225
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Telescoping light products, bank deposit drawers and securit
NAICS
n/a
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $10
M
to 50
M
# of Employees 295
Plant Area 169,000
ft2
Annual Production 10,200,000
lb
Production Hrs. Annual 3,300
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $190,737 4,332,405
kWh
Electricity Demand $43,438 844
kW-mo/yr
Natural Gas $46,644 12,230
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $65,166 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,130

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Administrative Changes Savings
01 2.2424: Use heat in flue gases to preheat products or materials $720 $4,100 - - $720
-
MMBtu
- -
02 2.2426: Use waste heat from flue gases to heat space conditioning air $6,690 $5,084 - - $6,690
-
MMBtu
- -
03 2.7111: Reduce illumination to minimum necessary levels $8,134 $528 $6,024
136,831
kWh
$2,110
-
kW-mo/yr
- - -
04 2.4157: Establish a predictive maintenance program $4,177 $1,320 $3,096
70,320
kWh
$1,081
-
kW-mo/yr
- - -
05 2.2437: Recover waste heat from equipment $674 $386 - - $674
-
MMBtu
- -
06 2.2414: Use waste heat from hot flue gases to preheat $2,187 $2,058 - - $2,187
-
MMBtu
- -
07 2.7241: Install outside air damper / economizer on hvac unit $1,519 $1,500 $1,122
25,491
kWh
$397
-
kW-mo/yr
- - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $453 $44 $335
7,618
kWh
$118
-
kW-mo/yr
- - -
09 2.4221: Install compressor air intakes in coolest locations $733 $104 $541
12,306
kWh
$192
-
kW-mo/yr
- - -
10 2.4111: Utilize energy-efficient belts and other improved mechanisms $683 $250 $400
9,083
kWh
$283
-
kW-mo/yr
- - -
11 2.2449: Recover heat from exhausted steam, hot air or hot water $2,221 $4,450 - - $2,221
-
MMBtu
- -
12 2.4231: Reduce the pressure of compressed air to the minimum required $699 $2,655 - - $699
-
MMBtu
- -
13 3.6193: Install equipment (eg compactor) to reduce disposal costs $275 $1,044 - - - $275
-
gal
-
14 3.6112: Use filter and drying oven to reduce sludge volume $1,001 $2,500 - - - $1,001
-
gal
-
15 4.513: Re-arrange equipment layout to reduce labor costs $35,000 $10,440 - - - - $35,000
TOTAL RECOMMENDED $65,166 $36,463 $11,518
261,649
kWh
$4,181
-
kW-mo/yr
$13,191
-
MMBtu
$1,276
-
gal
$35,000
TOTAL IMPLEMENTED $16,130 $6,176 $10,396
236,158
kWh
$3,784
-
kW-mo/yr
$674
-
MMBtu
$1,276
-
gal
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs