Assessment Year | 2001 |
---|---|
Principal Product | Hand soaps,Hand Cream and Lotion |
NAICS |
n/a
|
SIC | 2844: Perfumes, Cosmetics, and Other Toilet Preparations |
Sales Range | $50 M to 100M |
# of Employees | 400 |
Plant Area |
480,000
ft2
|
Annual Production | 10,200,000
lb
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $470,710 | 8,507,200 |
kWh
|
$0.055 |
Electricity Demand | $195,018 | 16,527 |
kW-mo/yr
|
$11.80 |
Natural Gas | $246,369 | 30,839 |
MMBtu
|
$7.99 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $238,684 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $93,565 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2121: Increase amount of condensate returned | $34,989 | $13,233 | - | - |
$34,989
-
MMBtu
|
- | - | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $6,320 | $5,782 | - | - |
$6,320
-
MMBtu
|
- | - | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $5,209 | $1,000 | - | - |
$5,209
-
MMBtu
|
- | - | |
04 | 2.2628: Utilize a less expensive cooling method | $3,489 | $2,436 |
$2,473
45,122
kWh
|
$1,016
-
kW-mo/yr
|
- | - | - | |
05 | 2.2511: Insulate bare equipment | $1,215 | $583 | - | - |
$1,215
-
MMBtu
|
- | - | |
06 | 2.2511: Insulate bare equipment | $1,103 | $120 | - | - |
$1,103
-
MMBtu
|
- | - | |
07 | 2.4157: Establish a predictive maintenance program | $13,668 | $2,160 |
$9,512
185,176
kWh
|
$4,156
-
kW-mo/yr
|
- | - | - | |
08 | 2.7111: Reduce illumination to minimum necessary levels | $13,361 | $2,160 |
$9,483
172,870
kWh
|
$3,878
-
kW-mo/yr
|
- | - | - | |
09 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $8,176 | $31,000 | - | - |
$8,176
-
MMBtu
|
- | - | |
10 | 3.5131: Recycle white water | $4,614 | $1,767 | - | - | - |
$4,614
-
Tgal
|
- | |
11 | 3.4115: Recover and reuse cooling water | $25,740 | $89,000 | - | - | - |
$25,740
-
Tgal
|
- | |
12 | 4.652: Replace existing equipment with more suitable substitutes | $20,000 | $14,000 | - | - | - | - | $20,000 | |
13 | 4.425: Eliminate/reduce redundant inspections | $100,800 | $19,200 | - | - | - | - | $100,800 | |
TOTAL RECOMMENDED | $238,684 | $182,441 |
$21,468
403,168
kWh
|
$9,050
-
kW-mo/yr
|
$57,012
-
MMBtu
|
$30,354
-
Tgal
|
$120,800 | ||
TOTAL IMPLEMENTED | $93,565 | $109,692 |
$21,468
403,168
kWh
|
$9,050
-
kW-mo/yr
|
$37,307
-
MMBtu
|
$25,740
-
Tgal
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs