| Assessment Year | 2001 |
|---|---|
| Principal Product | Hydraulic valves and manifolds |
| NAICS |
n/a
|
| SIC | 3492: Fluid Power Valves and Hose Fittings |
| Sales Range | $10 M to 50M |
| # of Employees | 125 |
| Plant Area |
49,000
ft2
|
| Annual Production | 120,000
pieces
|
| Production Hrs. Annual | 4,500
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $20,687 | 644,700 |
kWh
|
$0.032 |
| Electricity Demand | $15,344 | 190 |
kW-mo/yr
|
$80.76 |
| Natural Gas | $6,467 | 861 |
MMBtu
|
$7.51 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $78,486 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $24,157 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $889 | $100 |
$676
12,306
kWh
|
$213
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,960 | $2,070 |
$2,384
33,109
kWh
|
$576
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.2628: Utilize a less expensive cooling method | $659 | $1,140 |
$480
8,790
kWh
|
$179
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4157: Establish a predictive maintenance program | $7,765 | $600 |
$6,292
88,193
kWh
|
$1,713
-
kW-mo/yr
|
- | $(-240.0) | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $209 | $100 |
$160
2,930
kWh
|
$49
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.7111: Reduce illumination to minimum necessary levels | $7,137 | $21,787 |
$5,424
99,327
kWh
|
$1,713
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.7134: Use photocell controls | $548 | $300 |
$416
7,618
kWh
|
$132
-
kW-mo/yr
|
- | - | - | |
| 08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,318 | $40 |
$1,001
18,459
kWh
|
$317
-
kW-mo/yr
|
- | - | - | |
| 09 | 2.2511: Insulate bare equipment | $1,097 | $64 |
$832
15,236
kWh
|
$265
-
kW-mo/yr
|
- | - | - | |
| 10 | 2.7241: Install outside air damper / economizer on hvac unit | $1,137 | $4,500 |
$864
15,822
kWh
|
$273
-
kW-mo/yr
|
- | - | - | |
| 11 | 2.7232: Replace existing hvac unit with high efficiency model | $1,137 | $4,400 |
$864
15,822
kWh
|
$273
-
kW-mo/yr
|
- | - | - | |
| 12 | 3.6124: Burn waste oil for heat | $1,298 | $4,470 | - | - |
$1,298
-
gal
|
- | - | |
| 13 | 3.4155: Meter waste water | $2,332 | $800 | - | - | - | - | $2,332 | |
| 14 | 4.431: Train operators for maximum operating efficiency | $50,000 | $26,800 | - | - | - | - | $50,000 | |
| TOTAL RECOMMENDED | $78,486 | $67,171 |
$19,393
317,612
kWh
|
$5,703
-
kW-mo/yr
|
$1,298
-
gal
|
$(-240.0) | $52,332 | ||
| TOTAL IMPLEMENTED | $24,157 | $26,601 |
$17,089
275,420
kWh
|
$4,976
-
kW-mo/yr
|
- | $(-240.0) | $2,332 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs