ITAC Assessment: WV0219
ITAC logo
ITAC Assessment: WV0219
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Hydraulic valves and manifolds
NAICS
n/a
SIC 3492: Fluid Power Valves and Hose Fittings
Sales Range $10
M
to 50
M
# of Employees 125
Plant Area 49,000
ft2
Annual Production 120,000
pieces
Production Hrs. Annual 4,500
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $20,687 644,700
kWh
Electricity Demand $15,344 190
kW-mo/yr
Natural Gas $6,467 861
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $78,486 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,157

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $889 $100 $676
12,306
kWh
$213
-
kW-mo/yr
- - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,960 $2,070 $2,384
33,109
kWh
$576
-
kW-mo/yr
- - -
03 2.2628: Utilize a less expensive cooling method $659 $1,140 $480
8,790
kWh
$179
-
kW-mo/yr
- - -
04 2.4157: Establish a predictive maintenance program $7,765 $600 $6,292
88,193
kWh
$1,713
-
kW-mo/yr
- $(-240.0) -
05 2.4221: Install compressor air intakes in coolest locations $209 $100 $160
2,930
kWh
$49
-
kW-mo/yr
- - -
06 2.7111: Reduce illumination to minimum necessary levels $7,137 $21,787 $5,424
99,327
kWh
$1,713
-
kW-mo/yr
- - -
07 2.7134: Use photocell controls $548 $300 $416
7,618
kWh
$132
-
kW-mo/yr
- - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $1,318 $40 $1,001
18,459
kWh
$317
-
kW-mo/yr
- - -
09 2.2511: Insulate bare equipment $1,097 $64 $832
15,236
kWh
$265
-
kW-mo/yr
- - -
10 2.7241: Install outside air damper / economizer on hvac unit $1,137 $4,500 $864
15,822
kWh
$273
-
kW-mo/yr
- - -
11 2.7232: Replace existing hvac unit with high efficiency model $1,137 $4,400 $864
15,822
kWh
$273
-
kW-mo/yr
- - -
12 3.6124: Burn waste oil for heat $1,298 $4,470 - - $1,298
-
gal
- -
13 3.4155: Meter waste water $2,332 $800 - - - - $2,332
14 4.431: Train operators for maximum operating efficiency $50,000 $26,800 - - - - $50,000
TOTAL RECOMMENDED $78,486 $67,171 $19,393
317,612
kWh
$5,703
-
kW-mo/yr
$1,298
-
gal
$(-240.0) $52,332
TOTAL IMPLEMENTED $24,157 $26,601 $17,089
275,420
kWh
$4,976
-
kW-mo/yr
- $(-240.0) $2,332
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs